Which of the following is typically required during contract closeout procedures?
Correct Answer
A) Submission of as-built drawings and warranties
Contract closeout procedures typically include submission of as-built drawings, warranties, operation and maintenance manuals, final lien waivers, and other project documentation required for final completion.
Why This Is the Correct Answer
Contract closeout procedures occur at the end of a project and involve finalizing all documentation and transferring responsibility to the owner. As-built drawings show the actual construction as completed (which may differ from original plans), and warranties provide protection for the owner after project completion. These documents, along with operation manuals and lien waivers, are essential for the owner to properly maintain and operate the completed facility. This is a standard requirement in construction contracts and represents the contractor's final obligations before project completion.
Why the Other Options Are Wrong
Option B: Initial project scheduling
Initial project scheduling is a pre-construction activity that occurs after contract award but before construction begins. Closeout procedures happen at the end of the project when the schedule is being completed, not created.
Option D: Negotiation of the original contract price
Contract price negotiation occurs during the pre-construction phase, not during closeout. By the time closeout procedures begin, the contract price has already been established and any change orders have been processed throughout the project.
Memory Technique
Use the acronym 'WAOL' for closeout: Warranties, As-builts, Operation manuals, Lien waivers - these are the key deliverables when you're done building.
Reference Hint
Look up contract administration and project closeout procedures in your construction management or project administration reference materials, typically found in chapters covering project phases or contract administration.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Which cost estimating method is most appropriate for preliminary budgeting of a standard office building?
Next Question
A project requires disturbing 2.3 acres of land. Environmental permitting costs include $12,000 for wetland delineation, $8,500 for endangered species survey, and $450 per acre for stormwater management review. What is the total environmental permitting cost?