EstatePass
Contract AdminPermitshard20% of exam part

A project requires disturbing 2.3 acres of land. Environmental permitting costs include $12,000 for wetland delineation, $8,500 for endangered species survey, and $450 per acre for stormwater management review. What is the total environmental permitting cost?

Correct Answer

B) $22,035

The calculation is: $12,000 + $8,500 + (2.3 acres × $450) = $12,000 + $8,500 + $1,035 = $22,035. Environmental permitting often involves multiple cost components based on different regulatory requirements.

Answer Options
A
$21,985
B
$22,035
C
$22,485
D
$21,535

Why This Is the Correct Answer

Option B is correct because it properly adds all three environmental permitting cost components. The calculation includes the fixed costs for wetland delineation ($12,000) and endangered species survey ($8,500), plus the variable cost for stormwater management review calculated as 2.3 acres × $450 per acre = $1,035. The total is $12,000 + $8,500 + $1,035 = $22,035.

Why the Other Options Are Wrong

Option A: $21,985

Option D ($22,485) is incorrect because it overestimates the total by $450, which suggests the per-acre stormwater fee may have been added twice or calculated for 3.3 acres instead of 2.3 acres.

Option D: $21,535

Option A ($21,535) is incorrect because it appears to have miscalculated the per-acre stormwater management cost, likely using $450 for only 1.3 acres instead of the full 2.3 acres.

Memory Technique

Remember 'WES' - Wetland delineation, Endangered species survey, Stormwater management - to ensure you account for all three common environmental permitting cost categories.

Reference Hint

Florida Building Code Chapter 1, Section 105 - Permits and Environmental Compliance Requirements

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.