Which inspection is typically required FIRST for a new residential construction project in Hawaii?
Correct Answer
B) Footing inspection
Footing inspection is typically the first required inspection before concrete is poured for foundations.
Why This Is the Correct Answer
The footing inspection is the first required inspection in the construction sequence. It occurs before concrete is poured for the footings, allowing the inspector to verify that the excavation depth, width, and reinforcement are correct before the footings are permanently encased in concrete. This is the logical starting point since footings support everything built above them.
Why the Other Options Are Wrong
Option A: Foundation inspection
Foundation inspection comes after the footing inspection. The foundation is built upon the footings, so inspecting footings first (before concrete is poured) is required before the foundation inspection can occur.
Option C: Framing inspection
Framing inspection occurs much later in the construction sequence β after the foundation is complete and walls, floors, and roof framing are erected. It cannot be the first inspection.
Option D: Final inspection
Final inspection is the last inspection in the sequence, conducted when construction is complete and before the certificate of occupancy is issued. It is the opposite of the first inspection.
Memory Technique
Remember the construction sequence with the acronym 'FFFFF β Footing First, Foundation Follows, Framing, Final.' Or think of it like building a tower: you check the very bottom (footing) before you pour anything. Footings are below the foundation, so they're inspected before the foundation.
More Hawaii Questions
What is the minimum general liability insurance coverage required for Hawaii contractors under HRS 444?
A contractor's license expires on June 30th. What is the late renewal penalty fee in Hawaii?
A contractor completes $85,000 worth of work on a residential project in Hawaii. The property owner fails to pay. Under HRS 507, what is the maximum lien amount the contractor can claim?
A contractor's insurance policy has a $1 million aggregate limit and a $500,000 per occurrence limit. Two separate incidents occur: one causing $400,000 in damages and another causing $300,000. How much will the insurance cover?
Under Hawaii's mechanics lien law, a subcontractor must provide preliminary notice within how many days of first furnishing labor or materials?
A subcontractor provides $28,000 worth of plumbing work but is not paid by the general contractor. Under HRS 507, what is the priority of the mechanics lien compared to a mortgage recorded before construction began?
A contractor discovers contaminated soil during excavation of a residential property. Under Hawaii environmental regulations, who must be notified immediately?
A contractor working on a project in a Hawaii historic district must obtain approval from which entity before beginning work?
A contractor fails to obtain required building permits before starting work. The property owner discovers this and terminates the contract. Under Hawaii law, what is the contractor's right to payment?
A contractor has 12 employees with a total annual payroll of $480,000. If the workers compensation rate is $12.75 per $100 of payroll, what is the annual premium?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A contractor's general liability insurance policy has a $1,000,000 aggregate limit and $500,000 per occurrence limit. After three claims totaling $400,000, $300,000, and $250,000, how much coverage remains for additional claims?
Next Question
A contractor completes a $150,000 renovation project. The owner pays $120,000 but disputes the remaining $30,000. Under HRS 507, what preliminary notice requirement must the contractor have met to preserve lien rights?
