EstatePass
HawaiiBusiness & Lawhard50% of exam part

A contractor completes a $150,000 renovation project. The owner pays $120,000 but disputes the remaining $30,000. Under HRS 507, what preliminary notice requirement must the contractor have met to preserve lien rights?

Correct Answer

B) Notice must be given within 20 days of first providing labor or materials

HRS 507 requires contractors to provide preliminary notice within 20 days of first providing labor or materials to preserve their lien rights.

Answer Options
A
Notice must be given within 10 days of starting work
B
Notice must be given within 20 days of first providing labor or materials
C
No preliminary notice is required in Hawaii
D
Notice is only required for projects over $200,000

Why This Is the Correct Answer

HRS Chapter 507 (Hawaii's mechanics' lien statute) requires that a contractor or materialman provide preliminary notice within 20 days of first furnishing labor or materials to preserve the right to later file a lien. Missing this deadline extinguishes lien rights regardless of the validity of the underlying claim.

Why the Other Options Are Wrong

Option A: Notice must be given within 10 days of starting work

Ten days is not the statutory window under HRS 507. This is a fabricated timeframe; the correct period is 20 days. Confusing 10 days with 20 days is a common error on the exam.

Option C: No preliminary notice is required in Hawaii

Hawaii absolutely requires preliminary notice to preserve lien rights. Failing to serve timely preliminary notice forfeits a contractor's ability to record a mechanics' lien β€” one of the most powerful collection tools available.

Option D: Notice is only required for projects over $200,000

The preliminary notice requirement under HRS 507 applies to all covered projects; there is no dollar-amount threshold such as $200,000. Project size does not determine whether notice is required.

Memory Technique

Think '20/20 vision for liens': serve your notice within 20 days to keep your lien rights in clear view. If you miss those 20 days, your lien rights go blind.

Was this explanation helpful?

More Hawaii Questions

What is the minimum general liability insurance coverage required for Hawaii contractors under HRS 444?

A contractor's license expires on June 30th. What is the late renewal penalty fee in Hawaii?

A contractor completes $85,000 worth of work on a residential project in Hawaii. The property owner fails to pay. Under HRS 507, what is the maximum lien amount the contractor can claim?

A contractor's insurance policy has a $1 million aggregate limit and a $500,000 per occurrence limit. Two separate incidents occur: one causing $400,000 in damages and another causing $300,000. How much will the insurance cover?

Under Hawaii's mechanics lien law, a subcontractor must provide preliminary notice within how many days of first furnishing labor or materials?

A subcontractor provides $28,000 worth of plumbing work but is not paid by the general contractor. Under HRS 507, what is the priority of the mechanics lien compared to a mortgage recorded before construction began?

A contractor discovers contaminated soil during excavation of a residential property. Under Hawaii environmental regulations, who must be notified immediately?

A contractor working on a project in a Hawaii historic district must obtain approval from which entity before beginning work?

A contractor fails to obtain required building permits before starting work. The property owner discovers this and terminates the contract. Under Hawaii law, what is the contractor's right to payment?

A contractor has 12 employees with a total annual payroll of $480,000. If the workers compensation rate is $12.75 per $100 of payroll, what is the annual premium?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.