A contractor fails to obtain required building permits before starting work. The property owner discovers this and terminates the contract. Under Hawaii law, what is the contractor's right to payment?
Correct Answer
A) No payment until permits are obtained
Hawaii law generally prohibits payment to unlicensed contractors or those working without required permits until proper licensing and permits are obtained.
Why This Is the Correct Answer
Hawaii law strictly prohibits payment to contractors who work without required permits. This is a fundamental principle designed to protect property owners and ensure compliance with building codes and safety regulations. The contractor must obtain all necessary permits before being entitled to any payment, regardless of the quality or value of work performed. This requirement cannot be waived and serves as a strong deterrent against unpermitted construction work.
Why the Other Options Are Wrong
Option B: Full payment for work completed
Full payment is prohibited under Hawaii law when work is performed without required permits. The contractor has violated fundamental legal requirements by proceeding without permits, which voids their right to compensation regardless of work quality. Hawaii's strict permit compliance laws prevent contractors from benefiting financially from illegal construction activities.
Option C: Quantum meruit for value of work performed
Quantum meruit (payment for reasonable value of services) is not available to contractors who work without required permits in Hawaii. The state's public policy strongly favors permit compliance, and allowing quantum meruit recovery would undermine this policy by enabling contractors to profit from illegal work. The permit requirement is a prerequisite to any payment entitlement.
Option D: Payment minus permit costs and penalties
Simply deducting permit costs and penalties still allows the contractor to profit from illegal work performed without permits. Hawaii law requires complete permit compliance before any payment is due. Partial payment arrangements would weaken the deterrent effect of permit requirements and encourage contractors to proceed without proper authorization, violating public safety policies.
Memory Technique
Remember 'No Permit, No Pay' - Hawaii requires permits BEFORE payment, not after the fact.
More hi-law Questions
What is the minimum general liability insurance coverage required for Hawaii contractors under HRS 444?
A contractor's license expires on June 30th. What is the late renewal penalty fee in Hawaii?
A contractor completes $85,000 worth of work on a residential project in Hawaii. The property owner fails to pay. Under HRS 507, what is the maximum lien amount the contractor can claim?
A contractor's insurance policy has a $1 million aggregate limit and a $500,000 per occurrence limit. Two separate incidents occur: one causing $400,000 in damages and another causing $300,000. How much will the insurance cover?
Under Hawaii's mechanics lien law, a subcontractor must provide preliminary notice within how many days of first furnishing labor or materials?
A subcontractor provides $28,000 worth of plumbing work but is not paid by the general contractor. Under HRS 507, what is the priority of the mechanics lien compared to a mortgage recorded before construction began?
A contractor discovers contaminated soil during excavation of a residential property. Under Hawaii environmental regulations, who must be notified immediately?
A contractor working on a project in a Hawaii historic district must obtain approval from which entity before beginning work?
A contractor has 12 employees with a total annual payroll of $480,000. If the workers compensation rate is $12.75 per $100 of payroll, what is the annual premium?
A contractor discovers contaminated soil during excavation for a foundation in Hawaii. What is the first required action under state environmental regulations?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A mechanics lien is filed on June 1st for work completed on April 15th in Hawaii. When is the deadline to commence foreclosure action under HRS 507?
Next Question
A contractor discovers potential contaminated soil while excavating for a foundation in Hawaii. What is the contractor's immediate obligation?