A mechanics lien is filed on June 1st for work completed on April 15th in Hawaii. When is the deadline to commence foreclosure action under HRS 507?

Correct Answer

B) June 1st next year (1 year from filing)

Under HRS 507, foreclosure action must be commenced within one year from the date the lien was filed.

Answer Options
A
December 1st (6 months from filing)
B
June 1st next year (1 year from filing)
C
April 15th next year (1 year from completion)
D
December 1st (8 months from completion)

Why This Is the Correct Answer

Under Hawaii Revised Statutes Chapter 507, a party who files a mechanics lien must commence foreclosure action within one year from the date the lien was filed — not from the date work was completed or the date payment was due. Since the lien was filed June 1st, the foreclosure deadline is June 1st of the following year.

Why the Other Options Are Wrong

Option A: December 1st (6 months from filing)

Six months from filing (December 1st) is not the Hawaii statute of limitations for mechanics lien foreclosure. This timeframe may be confused with shorter deadlines in other states or with preliminary notice deadlines. Hawaii's HRS 507 sets a one-year period from filing.

Option C: April 15th next year (1 year from completion)

April 15th (one year from completion) is incorrect because the foreclosure clock runs from the lien filing date, not from the date work was completed. The completion date triggers the right to file a lien, but the foreclosure deadline is measured from the filing date.

Option D: December 1st (8 months from completion)

Eight months from completion (December 1st) does not correspond to any standard Hawaii mechanics lien provision. This answer conflates the completion date with the filing date and applies an incorrect time period.

Memory Technique

In Hawaii: FILE → 1 YEAR → FORECLOSE. The clock starts ticking the day you file. Think of the lien filing as 'planting the flag' — from that day, you have exactly one year to act on it in court. The date work ended is irrelevant to the foreclosure deadline.

Was this explanation helpful?

More hi-law Questions

What is the minimum general liability insurance coverage required for Hawaii contractors under HRS 444?

A contractor's license expires on June 30th. What is the late renewal penalty fee in Hawaii?

A contractor completes $85,000 worth of work on a residential project in Hawaii. The property owner fails to pay. Under HRS 507, what is the maximum lien amount the contractor can claim?

A contractor's insurance policy has a $1 million aggregate limit and a $500,000 per occurrence limit. Two separate incidents occur: one causing $400,000 in damages and another causing $300,000. How much will the insurance cover?

Under Hawaii's mechanics lien law, a subcontractor must provide preliminary notice within how many days of first furnishing labor or materials?

A subcontractor provides $28,000 worth of plumbing work but is not paid by the general contractor. Under HRS 507, what is the priority of the mechanics lien compared to a mortgage recorded before construction began?

A contractor discovers contaminated soil during excavation of a residential property. Under Hawaii environmental regulations, who must be notified immediately?

A contractor working on a project in a Hawaii historic district must obtain approval from which entity before beginning work?

A contractor fails to obtain required building permits before starting work. The property owner discovers this and terminates the contract. Under Hawaii law, what is the contractor's right to payment?

A contractor has 12 employees with a total annual payroll of $480,000. If the workers compensation rate is $12.75 per $100 of payroll, what is the annual premium?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.