Which document must be recorded in the county recorder's office to perfect a mechanics' lien in Arizona?
Correct Answer
D) Claim of lien
Under A.R.S. 33-981, the claim of lien must be recorded in the county recorder's office to perfect the mechanics' lien.
Why This Is the Correct Answer
Under A.R.S. 33-981, recording a Claim of Lien in the county recorder's office is the formal legal step that 'perfects' the mechanics' lien, making it enforceable against the property and binding on subsequent purchasers and lenders.
Why the Other Options Are Wrong
Option A: Notice of completion
A Notice of Completion is recorded by the owner to start the clock on lien filing deadlines β it does not itself perfect a lien. Confusing these two documents is a common error.
Option B: Notice to owner
A Notice to Owner is served on the property owner to preserve lien rights but is not recorded in the county recorder's office and does not by itself perfect the lien.
Option C: Preliminary 20-day notice
A Preliminary 20-Day Notice is served on the owner, lender, and general contractor within 20 days of first furnishing labor or materials. It is a prerequisite to filing a lien but is not the document recorded to perfect it.
Memory Technique
CLAIM = RECORDED. Think of 'claiming your territory on a map' β you record your Claim of Lien on the public record (county recorder) to mark your interest in the property.
More Arizona Questions
What is the current minimum bond amount required for a residential contractor license in Arizona?
A contractor files a preliminary 20-day notice on January 15th for work that began on January 10th. The preliminary notice was delivered to the owner on January 18th. Under A.R.S. 33-981, is this notice valid for lien purposes?
Under Arizona law, which entity has the authority to investigate complaints against licensed contractors and impose disciplinary actions?
Under Arizona ROC regulations, what is the maximum amount a residential contractor can collect as a down payment before beginning work?
A contractor's license expires on June 30th. The contractor submits a renewal application on July 15th. Under Arizona ROC regulations, what penalty applies?
A contractor's workers compensation policy lapses for 15 days due to non-payment of premiums. Three employees are injured during this period, resulting in $85,000 in medical costs. Under Arizona law, what is the contractor's potential liability?
According to A.R.S. Title 32, which of the following can serve as a qualifying party for multiple contracting businesses?
A residential contractor enters into a contract for $15,000 to remodel a kitchen. Under Arizona law, what is the required down payment limitation?
A residential contractor completed $45,000 in work and materials. The homeowner paid $35,000 but disputes the remaining $10,000. How long does the contractor have to file a mechanics lien after recording the notice of completion?
A contractor has 8 employees working on various projects. The annual workers' compensation premium is $24,000. If the contractor fails to maintain coverage, what is the maximum daily penalty exposure?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
According to A.R.S. Title 32, Chapter 10, what is the maximum monetary penalty the ROC can impose for a single violation of contracting regulations?
Next Question
A homeowner files a complaint against a residential contractor 18 months after project completion. Is the ROC likely to investigate this complaint?