EstatePass
Contract AdminPreconstructioneasy27% of exam part

Which cost estimating method would be most appropriate for a general contractor to use during the schematic design phase when detailed drawings are not yet available?

Correct Answer

B) Square foot method

The square foot method is most appropriate during schematic design when detailed information is limited. This method uses cost per square foot based on building type and can provide reasonable estimates with minimal design information.

Answer Options
A
Detailed quantity takeoff method
B
Square foot method
C
Unit price method
D
Assemblies method

Why This Is the Correct Answer

The square foot method is ideal for schematic design phase because it requires minimal information - just the building type and approximate square footage. During schematic design, detailed drawings, specifications, and material lists are not yet available, making this the only practical estimating method. It provides reasonable budget estimates using historical cost data per square foot for similar building types. This method aligns perfectly with the limited design information available at this early project phase.

Why the Other Options Are Wrong

Option A: Detailed quantity takeoff method

The unit price method requires knowing specific quantities of work items (linear feet of pipe, cubic yards of concrete, etc.) which cannot be determined without detailed drawings that don't exist in schematic design.

Option D: Assemblies method

The detailed quantity takeoff method requires complete drawings, specifications, and material lists to calculate exact quantities of every component. This level of detail is not available during schematic design phase.

Memory Technique

Think 'SIMPLE for SCHEMATIC' - when you have simple/limited information in schematic design, use the simple square foot method. As design progresses and gets more detailed, estimating methods become more detailed too.

Reference Hint

Look up 'Cost Estimating Methods' or 'Project Phases and Estimating' in construction management or estimating chapters of your reference materials.

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.