Which cost estimating method would be most appropriate for a general contractor to use during the schematic design phase when detailed drawings are not yet available?
Correct Answer
B) Square foot method
The square foot method is most appropriate during schematic design when detailed information is limited. This method uses cost per square foot based on building type and can provide reasonable estimates with minimal design information.
Why This Is the Correct Answer
The square foot method is ideal for schematic design phase because it requires minimal information - just the building type and approximate square footage. During schematic design, detailed drawings, specifications, and material lists are not yet available, making this the only practical estimating method. It provides reasonable budget estimates using historical cost data per square foot for similar building types. This method aligns perfectly with the limited design information available at this early project phase.
Why the Other Options Are Wrong
Option A: Detailed quantity takeoff method
The unit price method requires knowing specific quantities of work items (linear feet of pipe, cubic yards of concrete, etc.) which cannot be determined without detailed drawings that don't exist in schematic design.
Option D: Assemblies method
The detailed quantity takeoff method requires complete drawings, specifications, and material lists to calculate exact quantities of every component. This level of detail is not available during schematic design phase.
Memory Technique
Think 'SIMPLE for SCHEMATIC' - when you have simple/limited information in schematic design, use the simple square foot method. As design progresses and gets more detailed, estimating methods become more detailed too.
Reference Hint
Look up 'Cost Estimating Methods' or 'Project Phases and Estimating' in construction management or estimating chapters of your reference materials.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A quality control plan specifies that concrete strength tests must be performed on every 50 cubic yards of concrete placed. A foundation pour requires 275 cubic yards. How many strength tests are required?
Next Question
During the final inspection of a commercial building, the inspector notes that the fire sprinkler system test reports are missing. What is the most appropriate next step?
