EstatePass
Contract AdminProceduresmedium13% of exam part

A quality control plan specifies that concrete strength tests must be performed on every 50 cubic yards of concrete placed. A foundation pour requires 275 cubic yards. How many strength tests are required?

Correct Answer

D) 6 tests

275 ÷ 50 = 5.5, which rounds up to 6 tests. Quality control testing typically requires rounding up to ensure adequate coverage when the division doesn't result in a whole number.

Answer Options
A
5 tests
B
7 tests
C
8 tests
D
6 tests

Why This Is the Correct Answer

When dividing 275 cubic yards by 50 cubic yards per test, we get 5.5 tests. Since you cannot perform a partial test, quality control standards require rounding up to the next whole number to ensure complete coverage of the concrete pour. This means 6 tests are required to meet the specification that every 50 cubic yards must be tested. The rounding up principle ensures no portion of the concrete goes untested.

Why the Other Options Are Wrong

Option A: 5 tests

This answer uses only the whole number portion (5) from the division result of 5.5, but ignores the remaining 25 cubic yards that still need testing coverage.

Option B: 7 tests

This answer over-tests by one additional test beyond what's required, which would be wasteful and not follow the specified testing interval.

Option C: 8 tests

This answer significantly over-tests with three additional tests beyond what's required, which would be very wasteful and not follow the specified testing interval.

Memory Technique

Remember 'Round UP for QC' - Quality Control testing always rounds up because partial tests don't exist and all material must be covered.

Reference Hint

ACI 318 Building Code Requirements for Structural Concrete, Chapter 26 - Quality Control and Testing

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.