EstatePass
Contract AdminPreconstructioneasy27% of exam part

When preparing a detailed cost estimate for a commercial project, which cost estimating method provides the most accurate results?

Correct Answer

B) Detailed quantity takeoff with current pricing

Detailed quantity takeoff with current pricing provides the most accurate estimates because it involves measuring exact quantities of materials and labor required and applying current market prices to each item.

Answer Options
A
Assemblies method with unit costs
B
Detailed quantity takeoff with current pricing
C
Parametric estimating based on similar projects
D
Square foot method using historical data

Why This Is the Correct Answer

Detailed quantity takeoff with current pricing is the most accurate estimating method because it involves physically measuring and calculating the exact quantities of every material, labor hour, and equipment needed for the project. This method uses current market prices for each specific item rather than historical averages or assumptions. It accounts for the unique characteristics of each project and eliminates the guesswork inherent in other estimating methods. The accuracy comes from the granular level of detail and real-time pricing data.

Why the Other Options Are Wrong

Option A: Assemblies method with unit costs

The square foot method using historical data is less accurate because it relies on average costs per square foot from past projects, which may not reflect current market conditions or the specific complexities of the current project.

Option C: Parametric estimating based on similar projects

The assemblies method with unit costs is more accurate than square foot estimating but still less precise than detailed takeoffs because it groups items into assemblies rather than measuring each individual component separately.

Option D: Square foot method using historical data

Parametric estimating based on similar projects uses mathematical relationships and historical data from comparable projects, but it cannot account for the unique specifications and current market conditions of the specific project being estimated.

Memory Technique

Think 'DETAIL = ACCURATE' - Detailed takeoff gives you the exact recipe with current ingredient prices, while other methods are like estimating a meal cost without knowing exactly what's in it.

Reference Hint

Florida Building Code - Administrative Chapter 1, Section on Construction Documents and Cost Estimating Standards

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.