A concrete pour is scheduled for tomorrow, but the quality control checklist shows that rebar inspection has not been completed. The concrete supplier cannot reschedule without significant cost. What should the general contractor do?

Correct Answer

D) Complete the rebar inspection before proceeding with the pour

Quality control procedures must be followed in sequence. Rebar inspection must occur before concrete placement because once concrete is poured, the rebar cannot be properly inspected or corrected if deficient. The cost of rescheduling is less than the cost of potential structural problems.

Answer Options
A
Pour the concrete but document the deviation
B
Proceed with the pour and inspect the rebar later
C
Get written approval from the owner to proceed
D
Complete the rebar inspection before proceeding with the pour

Why This Is the Correct Answer

Option B is correct because quality control procedures must be followed in proper sequence, and rebar inspection is a critical step that must occur before concrete placement. Once concrete is poured, it becomes impossible to properly inspect the rebar placement, spacing, and tie connections. The structural integrity of the concrete depends on proper rebar installation, making this inspection non-negotiable. The short-term cost of rescheduling concrete delivery is minimal compared to the potential catastrophic costs of structural failure or having to demolish and rebuild defective work.

Why the Other Options Are Wrong

Option A: Pour the concrete but document the deviation

This violates fundamental quality control principles and creates serious safety risks. Once concrete hardens around the rebar, inspection becomes impossible, and any defects in rebar placement cannot be corrected without costly demolition.

Option B: Proceed with the pour and inspect the rebar later

Simply documenting a deviation does not make it acceptable. This approach still results in uninspected rebar being permanently encased in concrete, creating potential structural deficiencies that documentation cannot remedy.

Memory Technique

Use the acronym 'FIRST' - Finish Inspections before Reinforcement Solidifies in Time. Always inspect rebar FIRST before concrete pours.

Reference Hint

Florida Building Code Chapter 19 (Concrete) and ACI 318 for reinforcement inspection requirements

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.