EstatePass
North CarolinaNC Supplementmedium100% of exam part

What is the bond requirement for an unlimited North Carolina general contractor license?

Correct Answer

D) $50,000

NC unlimited general contractor licenses require a $50,000 bond under NC General Statutes Chapter 87.

Answer Options
A
$20,000
B
$25,000
C
$15,000
D
$50,000

Why This Is the Correct Answer

NC GS Chapter 87 and the NC Licensing Board for General Contractors require a $50,000 surety bond for contractors holding an unlimited license classification. The unlimited classification allows contractors to bid on projects of any dollar amount, and the higher bond requirement reflects the greater financial exposure.

Why the Other Options Are Wrong

Option A: $20,000

$20,000 is not a bond amount specified for any NC general contractor license tier. It may be confused with bond requirements in other states or with smaller specialty license categories.

Option B: $25,000

$25,000 is the bond requirement for the intermediate license classification in NC (projects between $500,000 and $1,000,000), not the unlimited classification.

Option C: $15,000

$15,000 is the bond requirement for the limited license classification in NC (projects up to $500,000), the lowest tier. Confusing this with the unlimited tier is a common error.

Memory Technique

NC bond tiers scale up: Limited = $15K, Intermediate = $25K, Unlimited = $50K. Think of it as doubling up: Limited to Intermediate roughly doubles ($15K → $25K), then Intermediate to Unlimited doubles again ($25K → $50K).

Was this explanation helpful?

More North Carolina Questions

A residential contractor in NC wants to bid on a $125,000 project but currently holds an Intermediate license. What action must be taken?

A contractor discovers contaminated soil during excavation on a commercial project in Charlotte. Under NC environmental regulations, what is the first required action?

A North Carolina contractor completes a $45,000 residential addition project. The homeowner refuses to pay the final $8,000. What is the filing deadline for a mechanic's lien under NC lien law?

A residential contractor in Charlotte is building a deck addition. Which inspection is typically required first under NC building codes?

A contractor performs work on a residential property in North Carolina but is not paid. The work was completed on March 15th, and the last material was delivered on March 20th. What is the deadline to file a claim of lien?

A subcontractor performing electrical work discovers that the general contractor's license has been suspended. What action should the subcontractor take according to NC General Statutes?

A contractor in North Carolina discovers contaminated soil during excavation. The soil contains petroleum products above reportable levels. Which agency must be notified immediately?

A contractor performing work on a North Carolina highway project encounters a suspected archaeological artifact. What is the required action under NC environmental regulations?

Calculate the workers' compensation premium for a NC roofing contractor with $250,000 in annual payroll and a rate of $18.50 per $100 of payroll:

Calculate the lien amount a subcontractor can claim on a $180,000 project where they provided $35,000 in materials and labor, but the general contractor still owes them $12,000:

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.