What is required for a contractor to reinstate a license that has been inactive for 18 months?
Correct Answer
B) Submit a new application with all requirements
After 12 months of inactivity, Arizona requires contractors to submit a completely new application and meet all current licensing requirements.
Why This Is the Correct Answer
Arizona law treats a license inactive for more than 12 months as effectively lapsed. After 12 months of inactivity, the contractor must submit a completely new application and satisfy all current licensing requirements — there is no shortcut reinstatement path.
Why the Other Options Are Wrong
Option A: Retake the trade examination
Retaking the trade exam is not the stated requirement for reinstatement in Arizona. While it might seem logical, the statutory requirement is a new application, which may or may not involve retesting depending on current requirements.
Option C: Complete 16 hours of continuing education
Completing 16 hours of continuing education alone is insufficient for reinstatement after 18 months of inactivity. CE hours may apply for standard renewal but not for reinstating a license that has been inactive beyond the 12-month threshold.
Option D: Pay renewal fees and penalties only
Paying renewal fees and penalties only applies when a license is moderately overdue, not when it has been inactive for 18 months (beyond the 12-month threshold). This shortcut is not available at 18 months.
Memory Technique
Think '12-month cliff' — once you go over 12 months inactive in Arizona, you fall off the cliff and must start completely fresh with a new application.
More Arizona Questions
What is the current minimum bond amount required for a residential contractor license in Arizona?
A contractor files a preliminary 20-day notice on January 15th for work that began on January 10th. The preliminary notice was delivered to the owner on January 18th. Under A.R.S. 33-981, is this notice valid for lien purposes?
Under Arizona law, which entity has the authority to investigate complaints against licensed contractors and impose disciplinary actions?
Under Arizona ROC regulations, what is the maximum amount a residential contractor can collect as a down payment before beginning work?
A contractor's license expires on June 30th. The contractor submits a renewal application on July 15th. Under Arizona ROC regulations, what penalty applies?
A contractor's workers compensation policy lapses for 15 days due to non-payment of premiums. Three employees are injured during this period, resulting in $85,000 in medical costs. Under Arizona law, what is the contractor's potential liability?
According to A.R.S. Title 32, which of the following can serve as a qualifying party for multiple contracting businesses?
A residential contractor enters into a contract for $15,000 to remodel a kitchen. Under Arizona law, what is the required down payment limitation?
A residential contractor completed $45,000 in work and materials. The homeowner paid $35,000 but disputes the remaining $10,000. How long does the contractor have to file a mechanics lien after recording the notice of completion?
A contractor has 8 employees working on various projects. The annual workers' compensation premium is $24,000. If the contractor fails to maintain coverage, what is the maximum daily penalty exposure?