Under the Louisiana Private Works Act, who has priority in lien claims?
Correct Answer
B) All valid liens share equal priority
Under Louisiana's Private Works Act, all valid privilege and lien claims that comply with statutory requirements share equal priority regardless of filing date or claimant type.
Why This Is the Correct Answer
Under Louisiana's Private Works Act (La. R.S. 9:4801 et seq.), all valid privilege and lien claims that comply with statutory requirements share equal priority (pari passu). The law intentionally avoids a first-filed-first-served hierarchy so that subcontractors, laborers, and materialmen are not disadvantaged simply because they file later than the general contractor.
Why the Other Options Are Wrong
Option A: General contractor always has first priority
The general contractor does not receive first priority simply by virtue of its role. Louisiana's parity principle means the GC's lien stands alongside all other valid claims on equal footing.
Option C: Liens rank by date of filing
Louisiana does not use a race-to-the-courthouse system for private works liens. Filing date does not determine rank; compliance with statutory requirements does.
Option D: Laborers and materialmen have priority over contractors
While laborers and materialmen are protected under the Act, they do not automatically rank above contractors. All qualifying claimants share equal priority, regardless of their position in the project hierarchy.
Memory Technique
Think 'Louisiana Levels the Playing Field' β all valid lien claimants stand on the same level platform, no one higher or lower. Contrast this with states where the date of first furnishing or filing determines rank.
More Louisiana Questions
A contractor in Louisiana completes $85,000 worth of work on a residential project. The owner pays $70,000 but disputes the remaining $15,000. If the contractor files a lien claim, what percentage penalty can be awarded if the contractor prevails in court?
A contractor discovers contaminated soil during excavation that requires special disposal. The disposal cost is $12,000, and transportation is $3,500. If this was not foreseeable from the contract documents, who typically bears this cost under Louisiana law?
A construction worker is injured on a Louisiana job site. The contractor's workers' compensation carrier has 15 days to investigate. If they don't respond within this period, what happens to the claim?
Under Louisiana law, what is the minimum amount of workers' compensation insurance coverage required for construction contractors?
A contractor's employee is injured on a job site in Louisiana. The contractor has workers' compensation insurance. Which statement is correct regarding the employee's rights?
Under Louisiana Civil Code, if a building contract does not specify a completion date, when is the work considered to be due?
Under Louisiana building codes, what is the minimum width required for emergency egress windows in bedrooms?
A Class B contractor in Louisiana wants to bid on a project worth $175,000. What action must they take?
A contractor's worker is injured and files for workers' compensation. The injury occurred due to the worker's intoxication. Under Louisiana law, what is the likely outcome?
A general contractor discovers contaminated soil during excavation for a commercial project in Louisiana. Which state agency must be notified?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A contractor's license in Louisiana expires on December 31st. The contractor submits a renewal application on February 15th of the following year. What additional penalty applies?
Next Question
A contractor performs $85,000 worth of electrical work on a commercial building in Louisiana. The required lien bond amount would be: