Under Tennessee lien law, when must a contractor provide preliminary notice to the property owner for work exceeding $3,000?

Correct Answer

C) Within 10 days of starting work

Tennessee lien law requires preliminary notice to be provided within 10 days of starting work on projects exceeding $3,000.

Answer Options
A
Before starting work
B
Within 10 days of completing work
C
Within 10 days of starting work
D
Within 30 days of starting work

Why This Is the Correct Answer

Tennessee lien law requires preliminary notice to be provided within 10 days of starting work on projects exceeding $3,000.

Was this explanation helpful?

More tn-supplement Questions

Calculate the Tennessee workers' compensation premium for a roofing contractor with a $180,000 annual payroll and a rate of $28.50 per $100 of payroll:

How many hours of continuing education are required for Tennessee contractor license renewal?

Calculate the workers' compensation experience modification factor for a contractor with $85,000 in expected losses and $68,000 in actual losses:

Under Tennessee lien law, what is the maximum time limit to enforce a mechanics lien after it has been filed?

Under Tennessee lien law, which party has priority when multiple liens are filed against the same property?

Under Tennessee building codes, what is the maximum allowable deflection for a residential floor joist with a 16-foot span under live load?

A homeowner in Nashville hires an unlicensed contractor for $8,000 worth of electrical work. The contractor demands payment but the work fails inspection. Under TCA 62-6, what recourse does the unlicensed contractor have?

Under Tennessee building codes, what is the minimum ceiling height required for habitable rooms in residential construction?

A Tennessee contractor has 8 employees working on a residential project. The total weekly payroll is $6,400. If the workers' compensation rate for residential construction is $8.50 per $100 of payroll, what is the weekly workers' compensation premium?

A contractor is installing a septic system for a new home in rural Tennessee. The estimated cost is $8,500. According to TCA 62-6, what licensing requirement applies?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.