Under TCA 62-6, a Tennessee contractor's license can be suspended for all of the following EXCEPT:
Correct Answer
A) Completing projects under budget
Completing projects under budget is not grounds for license suspension. The other options are all valid reasons for disciplinary action under TCA 62-6.
Why This Is the Correct Answer
Completing projects under budget is not grounds for license suspension. The other options are all valid reasons for disciplinary action under TCA 62-6.
More tn-supplement Questions
Calculate the Tennessee workers' compensation premium for a roofing contractor with a $180,000 annual payroll and a rate of $28.50 per $100 of payroll:
How many hours of continuing education are required for Tennessee contractor license renewal?
Calculate the workers' compensation experience modification factor for a contractor with $85,000 in expected losses and $68,000 in actual losses:
Under Tennessee lien law, what is the maximum time limit to enforce a mechanics lien after it has been filed?
Under Tennessee lien law, which party has priority when multiple liens are filed against the same property?
Under Tennessee building codes, what is the maximum allowable deflection for a residential floor joist with a 16-foot span under live load?
A homeowner in Nashville hires an unlicensed contractor for $8,000 worth of electrical work. The contractor demands payment but the work fails inspection. Under TCA 62-6, what recourse does the unlicensed contractor have?
Under Tennessee building codes, what is the minimum ceiling height required for habitable rooms in residential construction?
A Tennessee contractor has 8 employees working on a residential project. The total weekly payroll is $6,400. If the workers' compensation rate for residential construction is $8.50 per $100 of payroll, what is the weekly workers' compensation premium?
A contractor is installing a septic system for a new home in rural Tennessee. The estimated cost is $8,500. According to TCA 62-6, what licensing requirement applies?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Calculate the lien amount a subcontractor can claim for unpaid work totaling $15,000 on a project where the total contract value is $85,000 and the remaining balance owed to the general contractor is $8,000:
Next Question
A residential contractor receives a $35,000 down payment on a $140,000 project. According to Tennessee law, what is the maximum allowable down payment percentage?