Under NRS 108, what is the priority order for mechanics' lien claims on the same property?

Correct Answer

A) Based on the date work commenced

Under NRS 108, mechanics' liens generally have priority based on when work commenced on the property, not when the lien was filed.

Answer Options
A
Based on the date work commenced
B
All liens have equal priority
C
Based on the date the lien was filed
D
Based on the amount of the claim

Why This Is the Correct Answer

Under NRS 108, mechanics' liens generally have priority based on when work commenced on the property, not when the lien was filed.

Was this explanation helpful?

More nv-supplement Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.