Under NRS 108, what information must be included in a preliminary 20-day notice to preserve lien rights?
Correct Answer
B) Description of work, property address, and parties involved
NRS 108 requires preliminary notices to include a description of the work to be performed, the property address, and identification of the parties involved in the project to preserve lien rights.
Why This Is the Correct Answer
Option B is correct. NRS 108 specifies that a preliminary 20-day notice must identify the project with enough specificity to put the owner and other parties on notice. This requires: a description of the work to be performed or materials to be furnished, the address or legal description of the property, and identification of the parties involved (the claimant, the person who hired the claimant, and the property owner). These three elements together provide the essential framework for any future lien claim.
Why the Other Options Are Wrong
Option A: Contract amount and payment schedule
The contract amount and payment schedule are financial terms of the contract between the parties. NRS 108's preliminary notice is not a contract disclosure β it is a notice of potential lien rights. Contract terms are not required elements.
Option C: Only the contractor's name and license number
Only the contractor's name and license number is far too minimal. NRS 108 requires identification of all parties involved plus a description of the work and property β a license number alone does not put the property owner on meaningful notice.
Option D: Lien amount and filing deadline
The lien amount and filing deadline are elements of an actual lien claim, not a preliminary notice. At the time of serving a preliminary notice, the project is ongoing and no lien amount has been determined yet.
Memory Technique
The preliminary notice answers three questions: WHAT (description of work), WHERE (property address), and WHO (all parties). Think 'WWW' β the web of information that connects the lien claimant to the project.
More Nevada Questions
Under NRS 624, what is the minimum net worth requirement for a Class A General Contractor license in Nevada?
A Nevada contractor files a mechanics' lien for $45,000. What is the required bond amount to release this lien under NRS 108?
According to Nevada building codes, which edition of the International Building Code (IBC) is currently adopted for commercial construction?
A contractor receives a Notice of Disciplinary Action from the NSCB. Within how many days can they request a hearing to contest the action?
Which Nevada building code edition is currently adopted for commercial construction in most Nevada jurisdictions?
What is the minimum net worth requirement for a Nevada Class A general contractor license?
A contractor's employee is injured on a Nevada job site. The contractor lacks workers' compensation insurance. What is the potential penalty under NRS 624?
Under Nevada law, a contractor's workers' compensation insurance policy lapses on June 1st, and they continue working until June 15th before renewing. What is the potential consequence?
A general contractor hires a subcontractor who injures a worker on site. The subcontractor has no workers' compensation insurance. Under Nevada law, who is primarily liable for the claim?
A Nevada contractor fails to carry required workers' compensation insurance. What penalty can the Nevada Industrial Insurance System impose per day of non-compliance?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Which classification of Nevada contractor license is required to perform work valued at $2,500,000?
Next Question
A Nevada contractor discovers that their employee was injured on the job, but the contractor failed to carry workers' compensation insurance. What is the potential penalty under Nevada law?