EstatePass
NevadaNV B&Lhard100% of exam part

Under NRS 108, a material supplier delivers $15,000 worth of lumber to a residential project on March 1st and continues deliveries through March 15th. When must the preliminary notice be served to preserve lien rights?

Correct Answer

D) By March 21st

Under NRS 108, preliminary notice must be served within 20 days of first furnishing materials, which would be March 21st (20 days from March 1st).

Answer Options
A
By March 31st
B
By April 15th
C
By April 4th
D
By March 21st

Why This Is the Correct Answer

Under NRS 108.245, a material supplier must serve a preliminary notice within 20 days of FIRST furnishing materials to preserve lien rights for all subsequent deliveries. The first delivery was March 1st, so 20 days from March 1st = March 21st. Serving notice by March 21st protects the supplier's lien rights for all deliveries made from March 1st onward.

Why the Other Options Are Wrong

Option A: By March 31st

March 31st is 30 days from March 1st, which exceeds the 20-day window. Filing by this date would be too late to protect lien rights for the full period of deliveries.

Option B: By April 15th

April 15th is well past the 20-day deadline. By this date, lien rights for all deliveries would have been forfeited due to the missed notice deadline.

Option C: By April 4th

April 4th is 20 days from March 15th (the last delivery date). This would be correct only if the 20-day period ran from the LAST delivery, but NRS 108 starts the clock from the FIRST delivery, not the last.

Memory Technique

In Nevada, the 20-day clock starts ticking the moment the FIRST delivery arrives on site. Think of it as the 'first truck rule' β€” when the first truck delivers, your 20-day countdown begins immediately.

Was this explanation helpful?

More Nevada Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.