EstatePass
nv-supplementNevada Business & Lawmedium

Under Nevada law, within how many days must a contractor provide preliminary notice to preserve lien rights on a private project?

Correct Answer

D) 20 days

NRS 108 requires preliminary notice to be served within 20 days after first furnishing labor or materials on a private project to preserve lien rights.

Answer Options
A
10 days
B
15 days
C
30 days
D
20 days

Why This Is the Correct Answer

NRS 108 requires preliminary notice to be served within 20 days after first furnishing labor or materials on a private project to preserve lien rights.

Was this explanation helpful?

More nv-supplement Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.