Under NC General Statutes Chapter 87, what is the minimum insurance requirement for an unlimited general contractor?
Correct Answer
B) $500,000 general liability
NC General Statutes Chapter 87 requires unlimited general contractors to maintain $500,000 minimum general liability insurance.
Why This Is the Correct Answer
NC General Statutes Chapter 87 requires unlimited general contractors to maintain a minimum of $500,000 in general liability insurance. This higher threshold reflects the greater financial exposure of unlimited-license contractors who can take on projects of any value.
Why the Other Options Are Wrong
Option A: $100,000 general liability
$100,000 is insufficient for an unlimited license. This amount may be associated with lower license tiers or other trades but is not the NC Chapter 87 minimum for unlimited general contractors.
Option C: $50,000 general liability
$50,000 is far below the statutory minimum. This figure does not correspond to any recognized NC contractor insurance requirement.
Option D: $300,000 general liability
$300,000 is above $100,000 but below the required $500,000. It may appear plausible but does not meet the Chapter 87 requirement for unlimited licensees.
Memory Technique
Unlimited contractor = $500,000 minimum. Think: 'half a million for unlimited.' The bigger the license scope, the bigger the coverage floor.
More North Carolina Questions
A residential contractor in NC wants to bid on a $125,000 project but currently holds an Intermediate license. What action must be taken?
A contractor discovers contaminated soil during excavation on a commercial project in Charlotte. Under NC environmental regulations, what is the first required action?
A North Carolina contractor completes a $45,000 residential addition project. The homeowner refuses to pay the final $8,000. What is the filing deadline for a mechanic's lien under NC lien law?
A residential contractor in Charlotte is building a deck addition. Which inspection is typically required first under NC building codes?
A contractor performs work on a residential property in North Carolina but is not paid. The work was completed on March 15th, and the last material was delivered on March 20th. What is the deadline to file a claim of lien?
A subcontractor performing electrical work discovers that the general contractor's license has been suspended. What action should the subcontractor take according to NC General Statutes?
A contractor in North Carolina discovers contaminated soil during excavation. The soil contains petroleum products above reportable levels. Which agency must be notified immediately?
A contractor performing work on a North Carolina highway project encounters a suspected archaeological artifact. What is the required action under NC environmental regulations?
Calculate the workers' compensation premium for a NC roofing contractor with $250,000 in annual payroll and a rate of $18.50 per $100 of payroll:
Calculate the lien amount a subcontractor can claim on a $180,000 project where they provided $35,000 in materials and labor, but the general contractor still owes them $12,000:
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A contractor is bidding on a $750,000 commercial project in Charlotte. The estimated labor cost is $280,000. Using NC workers' compensation rates of $8.50 per $100 of payroll for this work classification, what is the workers' compensation insurance cost?
Next Question
According to NC General Statutes Chapter 87, what is the minimum dollar threshold for projects that require a licensed general contractor?