Under NC building codes, what is the maximum time period allowed between requesting an inspection and when the inspection must be performed?

Correct Answer

A) 2 business days

NC building codes require inspections to be performed within 2 business days of the request, excluding weekends and holidays.

Answer Options
A
2 business days
B
3 business days
C
1 business day
D
5 business days

Why This Is the Correct Answer

Option A (2 business days) is correct. NC building codes require building inspectors to perform inspections within 2 business days of a request, ensuring construction projects are not unreasonably delayed while maintaining code compliance oversight.

Why the Other Options Are Wrong

Option B: 3 business days

3 business days exceeds the NC statutory requirement. While 3 days might seem reasonable, NC law sets the standard at 2 business days to keep construction timelines moving.

Option C: 1 business day

1 business day is shorter than the required timeframe. Inspection departments need adequate scheduling time; a 1-day mandate would be operationally impractical for most jurisdictions and is not the NC standard.

Option D: 5 business days

5 business days is far longer than NC allows and would represent an unacceptable delay for contractors on tight schedules. This figure is not supported by NC building code inspection provisions.

Memory Technique

Two business days = 'Two-Day Turnaround.' NC gives inspectors a 2-day window β€” think of it as a 48-hour business rule. Weekends and holidays don't count, so a Friday request means the inspection must happen by Tuesday.

Was this explanation helpful?

More North Carolina Questions

A residential contractor in NC wants to bid on a $125,000 project but currently holds an Intermediate license. What action must be taken?

A contractor discovers contaminated soil during excavation on a commercial project in Charlotte. Under NC environmental regulations, what is the first required action?

A North Carolina contractor completes a $45,000 residential addition project. The homeowner refuses to pay the final $8,000. What is the filing deadline for a mechanic's lien under NC lien law?

A residential contractor in Charlotte is building a deck addition. Which inspection is typically required first under NC building codes?

A contractor performs work on a residential property in North Carolina but is not paid. The work was completed on March 15th, and the last material was delivered on March 20th. What is the deadline to file a claim of lien?

A subcontractor performing electrical work discovers that the general contractor's license has been suspended. What action should the subcontractor take according to NC General Statutes?

A contractor in North Carolina discovers contaminated soil during excavation. The soil contains petroleum products above reportable levels. Which agency must be notified immediately?

A contractor performing work on a North Carolina highway project encounters a suspected archaeological artifact. What is the required action under NC environmental regulations?

Calculate the workers' compensation premium for a NC roofing contractor with $250,000 in annual payroll and a rate of $18.50 per $100 of payroll:

Calculate the lien amount a subcontractor can claim on a $180,000 project where they provided $35,000 in materials and labor, but the general contractor still owes them $12,000:

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.