Under Louisiana's Private Works Act, what is the maximum time period a general contractor has to file a lien claim after the completion of work on a private construction project?

Correct Answer

A) 60 days

Under Louisiana's Private Works Act (La. R.S. 9:4801 et seq.), a general contractor must file a lien claim within 60 days after completion of the work.

Answer Options
A
60 days
B
90 days
C
120 days
D
30 days

Why This Is the Correct Answer

Louisiana's Private Works Act (La. R.S. 9:4801 et seq.) gives a general contractor 60 days from the completion of work to file a lien claim (statement of claim or privilege) against the owner's property. This is the standard deadline for GCs on private projects.

Why the Other Options Are Wrong

Option B: 90 days

90 days is the lien filing period in some other states (e.g., South Carolina for certain claimants) and is a common distractor. Louisiana's Private Works Act does not provide a 90-day window for general contractors.

Option C: 120 days

120 days is not a period established by Louisiana's Private Works Act for GC lien claims. It may be confused with bond claim periods or federal project timelines.

Option D: 30 days

30 days is too short and does not reflect the Louisiana Private Works Act's 60-day filing requirement for general contractors.

Memory Technique

60 days = 2 months. Picture the GC having exactly 'two calendar flips' after completing work to file their lien in Louisiana. Two months, two pages of the calendar.

Was this explanation helpful?

More Louisiana Questions

A contractor in Louisiana completes $85,000 worth of work on a residential project. The owner pays $70,000 but disputes the remaining $15,000. If the contractor files a lien claim, what percentage penalty can be awarded if the contractor prevails in court?

A contractor discovers contaminated soil during excavation that requires special disposal. The disposal cost is $12,000, and transportation is $3,500. If this was not foreseeable from the contract documents, who typically bears this cost under Louisiana law?

A construction worker is injured on a Louisiana job site. The contractor's workers' compensation carrier has 15 days to investigate. If they don't respond within this period, what happens to the claim?

Under Louisiana law, what is the minimum amount of workers' compensation insurance coverage required for construction contractors?

A contractor's employee is injured on a job site in Louisiana. The contractor has workers' compensation insurance. Which statement is correct regarding the employee's rights?

Under Louisiana Civil Code, if a building contract does not specify a completion date, when is the work considered to be due?

Under Louisiana building codes, what is the minimum width required for emergency egress windows in bedrooms?

A Class B contractor in Louisiana wants to bid on a project worth $175,000. What action must they take?

A contractor's worker is injured and files for workers' compensation. The injury occurred due to the worker's intoxication. Under Louisiana law, what is the likely outcome?

A general contractor discovers contaminated soil during excavation for a commercial project in Louisiana. Which state agency must be notified?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.