Under Louisiana Civil Code, what is the warranty period for major structural defects in residential construction?
Correct Answer
D) 10 years
Louisiana Civil Code provides a 10-year warranty period for major structural defects in residential construction.
Why This Is the Correct Answer
Louisiana Civil Code Article 2762 and the New Home Warranty Act (La. R.S. 9:3141) provide a 10-year warranty for major structural defects in residential construction. This decennial liability period is one of the most distinctive features of Louisiana construction law, rooted in the French Civil Code tradition.
Why the Other Options Are Wrong
Option A: 1 year
1 year is insufficient. A 1-year warranty typically covers workmanship and materials defects under the Louisiana New Home Warranty Act, but major structural defects carry a much longer 10-year period.
Option B: 5 years
5 years is not the correct warranty period for major structural defects under Louisiana law. This figure may be confused with mid-tier warranty periods in other states.
Option C: 2 years
2 years is a warranty period for certain mechanical systems (plumbing, electrical, HVAC) under the Louisiana New Home Warranty Act, not for major structural defects.
Memory Technique
Louisiana's 'Decade of Structure': major structural defects are covered for a full 10 years. Remember the three tiers: 1-2-10 (workmanship, systems, structure).
More Louisiana Questions
A contractor in Louisiana completes $85,000 worth of work on a residential project. The owner pays $70,000 but disputes the remaining $15,000. If the contractor files a lien claim, what percentage penalty can be awarded if the contractor prevails in court?
A contractor discovers contaminated soil during excavation that requires special disposal. The disposal cost is $12,000, and transportation is $3,500. If this was not foreseeable from the contract documents, who typically bears this cost under Louisiana law?
A construction worker is injured on a Louisiana job site. The contractor's workers' compensation carrier has 15 days to investigate. If they don't respond within this period, what happens to the claim?
Under Louisiana law, what is the minimum amount of workers' compensation insurance coverage required for construction contractors?
A contractor's employee is injured on a job site in Louisiana. The contractor has workers' compensation insurance. Which statement is correct regarding the employee's rights?
Under Louisiana Civil Code, if a building contract does not specify a completion date, when is the work considered to be due?
Under Louisiana building codes, what is the minimum width required for emergency egress windows in bedrooms?
A Class B contractor in Louisiana wants to bid on a project worth $175,000. What action must they take?
A contractor's worker is injured and files for workers' compensation. The injury occurred due to the worker's intoxication. Under Louisiana law, what is the likely outcome?
A general contractor discovers contaminated soil during excavation for a commercial project in Louisiana. Which state agency must be notified?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass