Under Louisiana Civil Code, what is the prescriptive period for filing a lawsuit for construction defects on a residential building?

Correct Answer

C) 10 years from completion

Louisiana Civil Code Article 3498 establishes a 10-year prescriptive period for construction defect claims on immovable property from the time of completion.

Answer Options
A
5 years from completion
B
2 years from discovery
C
10 years from completion
D
1 year from discovery

Why This Is the Correct Answer

10 years from completion is correct under Louisiana Civil Code Article 3498 (and the related Article 2762). Louisiana imposes a 10-year peremptive/prescriptive period for claims arising from defects in immovable property construction. This 10-year period runs from the date the work is completed, regardless of when the defect is discovered. This is a notably long period compared to many other states and reflects Louisiana's civil law tradition.

Why the Other Options Are Wrong

Option A: 5 years from completion

5 years from completion is not the Louisiana standard for construction defect claims on immovable property. While some Louisiana contractual claims may prescribe in 5 years, the specific construction defect period under Civil Code Article 3498 is 10 years.

Option B: 2 years from discovery

2 years from discovery applies to certain personal injury tort claims in Louisiana (like delictual actions), not to construction defect claims on immovable property. Applying a discovery rule here confuses two different prescriptive frameworks.

Option D: 1 year from discovery

1 year from discovery is Louisiana's standard prescription for delictual (tort) actions, such as negligence claims. However, construction defect claims on buildings follow the longer 10-year period from completion, not the 1-year tort prescription.

Memory Technique

Remember 'LA buildings get a decade': Louisiana gives property owners 10 years from completion to sue for construction defects. Associate '10' with the 10 letters in 'Louisiana' to lock it in memory.

Was this explanation helpful?

More Louisiana Questions

A contractor in Louisiana completes $85,000 worth of work on a residential project. The owner pays $70,000 but disputes the remaining $15,000. If the contractor files a lien claim, what percentage penalty can be awarded if the contractor prevails in court?

A contractor discovers contaminated soil during excavation that requires special disposal. The disposal cost is $12,000, and transportation is $3,500. If this was not foreseeable from the contract documents, who typically bears this cost under Louisiana law?

A construction worker is injured on a Louisiana job site. The contractor's workers' compensation carrier has 15 days to investigate. If they don't respond within this period, what happens to the claim?

Under Louisiana law, what is the minimum amount of workers' compensation insurance coverage required for construction contractors?

A contractor's employee is injured on a job site in Louisiana. The contractor has workers' compensation insurance. Which statement is correct regarding the employee's rights?

Under Louisiana Civil Code, if a building contract does not specify a completion date, when is the work considered to be due?

Under Louisiana building codes, what is the minimum width required for emergency egress windows in bedrooms?

A Class B contractor in Louisiana wants to bid on a project worth $175,000. What action must they take?

A contractor's worker is injured and files for workers' compensation. The injury occurred due to the worker's intoxication. Under Louisiana law, what is the likely outcome?

A general contractor discovers contaminated soil during excavation for a commercial project in Louisiana. Which state agency must be notified?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.