EstatePass
ArizonaAZ B&Lhard100% of exam part

Under Arizona law, a contractor completes a $35,000 home addition on March 15th. The final payment of $5,000 becomes due April 1st but remains unpaid. If the contractor files a lien on July 20th, what is the status of this lien?

Correct Answer

B) Invalid, filed more than 120 days after completion

The lien was filed 127 days after completion (March 15 to July 20), exceeding the 120-day requirement under A.R.S. 33-981, making it invalid.

Answer Options
A
Invalid, residential liens must be filed within 90 days
B
Invalid, filed more than 120 days after completion
C
Valid, but only if preliminary notice was properly served
D
Valid, filed within the 120-day requirement

Why This Is the Correct Answer

Under A.R.S. 33-981, a contractor must file a mechanics lien within 120 days of project completion. Completion occurred March 15th; 120 days later is July 13th. The lien was filed July 20th — 127 days after completion — making it untimely and therefore invalid.

Why the Other Options Are Wrong

Option A: Invalid, residential liens must be filed within 90 days

The claim that residential liens must be filed within 90 days is incorrect. Arizona's statutory deadline under A.R.S. 33-981 is 120 days from completion, not 90 days.

Option C: Valid, but only if preliminary notice was properly served

While preliminary notice is indeed a requirement for lien rights, the lien here is invalid not because of a preliminary notice defect but because it was filed beyond the 120-day deadline. Timely filing is a threshold requirement regardless of preliminary notice.

Option D: Valid, filed within the 120-day requirement

The lien was not filed within the 120-day requirement. March 15 + 120 days = July 13. The lien was filed July 20 — seven days late — making this statement factually incorrect.

Memory Technique

Count from completion: March 15 → April 15 (30 days) → May 15 (60 days) → June 15 (90 days) → July 13 (120 days). July 20 is past the deadline by 7 days. Use a month-by-month counting method to avoid arithmetic errors on the exam.

Was this explanation helpful?

More Arizona Questions

What is the current minimum bond amount required for a residential contractor license in Arizona?

A contractor files a preliminary 20-day notice on January 15th for work that began on January 10th. The preliminary notice was delivered to the owner on January 18th. Under A.R.S. 33-981, is this notice valid for lien purposes?

Under Arizona law, which entity has the authority to investigate complaints against licensed contractors and impose disciplinary actions?

Under Arizona ROC regulations, what is the maximum amount a residential contractor can collect as a down payment before beginning work?

A contractor's license expires on June 30th. The contractor submits a renewal application on July 15th. Under Arizona ROC regulations, what penalty applies?

A contractor's workers compensation policy lapses for 15 days due to non-payment of premiums. Three employees are injured during this period, resulting in $85,000 in medical costs. Under Arizona law, what is the contractor's potential liability?

According to A.R.S. Title 32, which of the following can serve as a qualifying party for multiple contracting businesses?

A residential contractor enters into a contract for $15,000 to remodel a kitchen. Under Arizona law, what is the required down payment limitation?

A residential contractor completed $45,000 in work and materials. The homeowner paid $35,000 but disputes the remaining $10,000. How long does the contractor have to file a mechanics lien after recording the notice of completion?

A contractor has 8 employees working on various projects. The annual workers' compensation premium is $24,000. If the contractor fails to maintain coverage, what is the maximum daily penalty exposure?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.