In sustainable construction, what does the term 'embodied energy' refer to?
Correct Answer
B) Energy required to produce and transport materials
Embodied energy refers to the total energy required to extract, process, manufacture, and transport building materials to the construction site.
Why This Is the Correct Answer
Embodied energy is a fundamental concept in sustainable construction that quantifies the total energy investment required before a material even reaches the construction site. This includes energy used in raw material extraction (mining, harvesting), processing and manufacturing, and transportation to the project location. Understanding embodied energy helps contractors make informed decisions about material selection to minimize environmental impact. This concept is distinct from operational energy, which occurs after construction is complete.
Why the Other Options Are Wrong
Option A: Energy efficiency rating of the completed building
This describes energy performance ratings like ENERGY STAR or LEED ratings that measure how efficiently a completed building uses energy during operation, not the energy invested in creating the building materials.
Option D: Energy stored in renewable building systems
This describes energy storage capacity of renewable systems like solar panels or batteries, which is unrelated to embodied energy. Embodied energy is about the energy invested in creating materials, not storing energy for later use.
Memory Technique
Think 'EMBODIED = EMBEDDED' - the energy is embedded in the material from Extract, Manufacture, and Bring (transport) to site. Remember EMB for the three main phases.
Reference Hint
Look up sustainable construction practices or green building chapters in your Florida Building Code or construction management reference materials, particularly sections on material selection and environmental impact.
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
In a Guaranteed Maximum Price (GMP) contract with a shared savings clause, the final project cost is $2,850,000 and the GMP was set at $3,100,000. If the savings are split 50/50 between owner and contractor, how much additional compensation does the contractor receive?
Next Question
In a cost-plus-fee contract with a 12% fee, if the actual project costs are $420,000 and there was a $15,000 cost overrun due to owner changes, what is the total amount due to the contractor?