In a cost-plus-fee contract with a 12% fee, if the actual project costs are $420,000 and there was a $15,000 cost overrun due to owner changes, what is the total amount due to the contractor?

Correct Answer

C) $487,200

Total costs including overrun: $420,000 + $15,000 = $435,000. Fee: $435,000 × 12% = $52,200. Total due: $435,000 + $52,200 = $487,200.

Answer Options
A
$472,200
B
$485,400
C
$487,200
D
$470,400

Why This Is the Correct Answer

In a cost-plus-fee contract, the contractor is reimbursed for all legitimate project costs plus a predetermined fee percentage. The total project costs include both the original costs ($420,000) and any approved cost overruns ($15,000), totaling $435,000. The 12% fee is calculated on the entire cost basis of $435,000, resulting in a fee of $52,200. The total amount due is the sum of all costs plus the fee: $435,000 + $52,200 = $487,200.

Why the Other Options Are Wrong

Option A: $472,200

This answer incorrectly calculates the fee on only the original project costs ($420,000 × 12% = $50,400) instead of on the total costs including overruns, resulting in $420,000 + $15,000 + $50,400 = $485,400, but shows as $472,200 which suggests a calculation error.

Option B: $485,400

This answer incorrectly calculates the fee on only the original project costs ($420,000 × 12% = $50,400) and adds it to the total costs including overrun ($420,000 + $15,000 + $50,400 = $485,400), but the fee should be calculated on the total costs including overruns.

Memory Technique

Remember 'TOTAL before FEE' - always calculate the fee percentage on the total project costs (including overruns), not just the original estimate.

Reference Hint

Look up contract types and payment methods in Chapter 4 (Project Management) or Chapter 6 (Construction Contracts) of your Florida contractor exam reference guide.

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.