In resource leveling for a construction project, you have 8 carpenters available but your schedule shows peak demand of 12 carpenters for 3 days. What is the most cost-effective solution?

Correct Answer

C) Use temporary labor for the 3-day peak period

For a short-term peak demand (3 days), temporary labor is the most cost-effective solution rather than permanent hiring or major schedule changes.

Answer Options
A
Hire 4 additional permanent carpenters
B
Subcontract the entire carpentry scope
C
Use temporary labor for the 3-day peak period
D
Extend the schedule to reduce peak demand

Why This Is the Correct Answer

For a short-term peak demand (3 days), temporary labor is the most cost-effective solution rather than permanent hiring or major schedule changes.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.