A quality control inspection reveals that 15% of installed drywall joints fail to meet specifications. The total drywall area is 50,000 square feet, and remediation costs $2.50 per square foot for failed areas. What is the total remediation cost?
Correct Answer
D) $18,750
Failed area: 50,000 × 0.15 = 7,500 sq ft. Remediation cost: 7,500 × $2.50 = $18,750.
Why This Is the Correct Answer
Failed area: 50,000 × 0.15 = 7,500 sq ft. Remediation cost: 7,500 × $2.50 = $18,750.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
During a quality control inspection, you discover that installed electrical conduit does not match the approved shop drawings. The work appears functional but differs from specifications. What is the proper procedure?
Next Question
In resource leveling for a construction project, you have 8 carpenters available but your schedule shows peak demand of 12 carpenters for 3 days. What is the most cost-effective solution?
