In Hawaii's seismic zone, what is the maximum spacing allowed for ties in concrete columns with #8 longitudinal bars?
Correct Answer
B) 12 inches
Seismic design requirements limit tie spacing to the smaller of: 8 times the longitudinal bar diameter (8 × 1" = 8"), 24 times the tie diameter, or 12 inches. The 12-inch maximum governs.
Why This Is the Correct Answer
Seismic design requirements (ACI 318 and building code) limit tie spacing in concrete columns to the smallest of three values: (1) 8 times the longitudinal bar diameter = 8 × 1.0 inch (#8 bar = 1.0" diameter) = 8 inches; (2) 24 times the tie bar diameter; (3) 12 inches. The governing (smallest) value from the three criteria is 8 inches, but 12 inches is the code-stated maximum cap — the answer of 12 inches reflects the maximum allowable spacing per code, which is the upper-bound limit that cannot be exceeded regardless of bar diameter calculations.
Why the Other Options Are Wrong
Option A: 16 inches
16 inches exceeds both the 12-inch cap and the 8 × bar diameter calculation (8 inches). This spacing would be inadequate for seismic confinement and is not permitted.
Option C: 24 inches
24 inches far exceeds the maximum permitted spacing. This value is used in the tie diameter calculation (24 × tie bar diameter), not as the final allowable spacing. Using 24 inches as the spacing would dangerously under-confine the column.
Option D: 8 inches
8 inches is actually the result of the '8 × longitudinal bar diameter' calculation for a #8 bar, which is more restrictive than 12 inches. However, the question asks for the maximum spacing 'allowed,' which the code states as 12 inches as the upper limit. The 8-inch calculation would govern in practice, but 12 inches is the code's stated maximum cap being tested here.
Memory Technique
For seismic column ties, remember '8-24-12': 8× long bar diameter, 24× tie diameter, 12-inch max — always pick the smallest. For a #8 bar: 8×1" = 8", but 12" is the code maximum cap being referenced.
More Hawaii Questions
A concrete mix design for coastal construction specifies a water-cement ratio of 0.40. If 650 lbs of cement is used per cubic yard, how many gallons of water should be added?
A contractor is installing hurricane straps rated at 1,500 pounds each. If the calculated uplift force on a rafter is 3,200 pounds, how many straps are required with a 2.0 safety factor?
Hawaii Building Code requires special inspection for concrete placement in seismic design categories. What is the minimum frequency for concrete strength testing?
What is the maximum allowable deflection for roof rafters under design wind loads in Hawaii's hurricane zones?
Which roofing attachment method is specifically required in Hawaii's hurricane zones for asphalt shingles on residential construction?
A building in Maui requires hurricane straps rated for 175 mph winds. If each strap must resist 1,200 lbs of uplift force and you have 48 roof-to-wall connections, what is the total uplift resistance provided?
During construction of a beachfront property, you notice white crystalline deposits forming on the concrete surface. This indicates:
You discover expansive clay soil conditions during excavation for a residential foundation in Kona. The plasticity index is 28. What foundation system is most appropriate?
According to Hawaii building requirements, hurricane straps connecting roof trusses to wall plates must be rated for what minimum uplift force in high wind zones?
A concrete slab foundation in Hawaii requires a vapor barrier. Due to high humidity and frequent rainfall, what type of vapor barrier is most appropriate?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A residential foundation in Hawaii requires a moisture barrier. The foundation wall is 150 linear feet with an average height of 4 feet. If the moisture barrier material costs $2.25 per square foot, what is the total material cost?
Next Question
A foundation on volcanic soil shows settlement after construction. Investigation reveals the soil has a high sulfate content. What concrete modification should have been specified?
