EstatePass
hi-tradeHawaii Trade Exammedium

A contractor is installing hurricane straps rated at 1,500 pounds each. If the calculated uplift force on a rafter is 3,200 pounds, how many straps are required with a 2.0 safety factor?

Correct Answer

B) 5 straps

Required capacity = 3,200 lbs × 2.0 = 6,400 lbs. Number of straps = 6,400 ÷ 1,500 = 4.27, round up to 5 straps minimum.

Answer Options
A
6 straps
B
5 straps
C
3 straps
D
4 straps

Why This Is the Correct Answer

Option B is correct because the total required capacity is 3,200 lbs × 2.0 safety factor = 6,400 lbs. Dividing by each strap's 1,500 lb capacity gives 6,400 ÷ 1,500 = 4.27 straps. Since you cannot install a partial strap, this must be rounded up to 5 complete straps to meet the safety requirements. This ensures adequate structural protection against hurricane uplift forces.

Why the Other Options Are Wrong

Option A: 6 straps

6 straps would provide 9,000 lbs capacity (6 × 1,500), which exceeds the required 6,400 lbs. While this would be safe, it's unnecessarily conservative and wasteful of materials and labor costs.

Option C: 3 straps

3 straps would only provide 4,500 lbs capacity (3 × 1,500), which is significantly less than the required 6,400 lbs with safety factor. This would create a dangerous structural deficiency.

Option D: 4 straps

4 straps would provide 6,000 lbs capacity (4 × 1,500), which falls short of the required 6,400 lbs with the 2.0 safety factor. This creates an unsafe condition that doesn't meet code requirements.

Memory Technique

Remember 'Safety First, Round Up': Always multiply by safety factor FIRST, then divide by strap capacity, and always round UP to the next whole number of straps.

Was this explanation helpful?

More hi-trade Questions

A concrete mix design for coastal construction specifies a water-cement ratio of 0.40. If 650 lbs of cement is used per cubic yard, how many gallons of water should be added?

Hawaii Building Code requires special inspection for concrete placement in seismic design categories. What is the minimum frequency for concrete strength testing?

What is the maximum allowable deflection for roof rafters under design wind loads in Hawaii's hurricane zones?

Which roofing attachment method is specifically required in Hawaii's hurricane zones for asphalt shingles on residential construction?

A building in Maui requires hurricane straps rated for 175 mph winds. If each strap must resist 1,200 lbs of uplift force and you have 48 roof-to-wall connections, what is the total uplift resistance provided?

During construction of a beachfront property, you notice white crystalline deposits forming on the concrete surface. This indicates:

You discover expansive clay soil conditions during excavation for a residential foundation in Kona. The plasticity index is 28. What foundation system is most appropriate?

According to Hawaii building requirements, hurricane straps connecting roof trusses to wall plates must be rated for what minimum uplift force in high wind zones?

A concrete slab foundation in Hawaii requires a vapor barrier. Due to high humidity and frequent rainfall, what type of vapor barrier is most appropriate?

A concrete slab in Hawaii requires a vapor barrier due to moisture conditions. The slab area is 1,200 sq ft and vapor barrier costs $0.85 per sq ft including 10% waste factor. What is the total material cost?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.