In a unit price contract for roadwork, the bid includes 5,000 cubic yards of concrete at $120 per cubic yard. The actual quantity used is 5,800 cubic yards. What is the total payment for concrete work?

Correct Answer

C) $696,000

In a unit price contract, payment is based on actual quantities used, not the estimated bid quantities. The total payment is 5,800 cubic yards × $120 per cubic yard = $696,000.

Answer Options
A
$756,000
B
$720,000
C
$696,000
D
$600,000

Why This Is the Correct Answer

In a unit price contract, payment is calculated based on the actual quantities of work performed, not the estimated quantities in the original bid. The contractor is paid for the exact amount of materials used or work completed at the agreed unit price. Since 5,800 cubic yards were actually used at $120 per cubic yard, the total payment is $696,000. This protects both parties when actual quantities differ from estimates.

Why the Other Options Are Wrong

Option A: $756,000

This appears to use an incorrect calculation or wrong unit price. The correct calculation is 5,800 × $120 = $696,000, not $720,000.

Option B: $720,000

This uses the original bid quantity (5,000 cubic yards) instead of the actual quantity used (5,800 cubic yards). In unit price contracts, payment must be based on actual work performed.

Option D: $600,000

This uses an incorrect calculation that doesn't match either the bid quantity or actual quantity at the stated unit price of $120 per cubic yard.

Memory Technique

Think 'ACTUAL PAYS' - in unit price contracts, you get paid for ACTUAL work performed, not estimated quantities.

Reference Hint

Florida Building Code Chapter 1, Contract Administration section, or construction contract law references covering unit price contract types

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.