EstatePass
Contract AdminContractshard40% of exam part

In a Guaranteed Maximum Price (GMP) contract with shared savings, the GMP is $750,000 with actual costs of $720,000. If savings are split 50/50, how much does the contractor receive?

Correct Answer

D) $735,000

The savings are $750,000 - $720,000 = $30,000. With 50/50 sharing, the contractor receives actual costs plus half the savings: $720,000 + ($30,000 × 0.50) = $735,000.

Answer Options
A
$745,000
B
$750,000
C
$720,000
D
$735,000

Why This Is the Correct Answer

In a GMP contract with shared savings, the contractor receives their actual costs plus their share of any savings achieved. The savings of $30,000 ($750,000 - $720,000) are split 50/50 between owner and contractor. Therefore, the contractor receives $720,000 (actual costs) + $15,000 (50% of savings) = $735,000. This incentivizes contractors to control costs while ensuring they're compensated fairly.

Why the Other Options Are Wrong

Option A: $745,000

This represents only the actual costs ($720,000) without including the contractor's share of the savings. In a shared savings GMP contract, the contractor is entitled to their portion of any cost savings achieved below the guaranteed maximum price.

Option B: $750,000

This amount ($745,000) incorrectly gives the contractor 83.3% of the savings instead of the specified 50%. It appears to split the total difference between actual costs and GMP in half, rather than calculating shared savings properly.

Option C: $720,000

This is the original GMP amount ($750,000), which would only be paid if actual costs equaled the GMP. Since actual costs were lower, the contractor receives actual costs plus their share of savings, not the full GMP amount.

Memory Technique

Think 'GMP = Give Me Plus': Contractor gets actual costs PLUS their share of savings. Never just actual costs alone, never the full GMP if costs are lower.

Reference Hint

Look up 'Guaranteed Maximum Price Contracts' and 'Cost-Plus Contracts with Shared Savings' in the AIA Contract Documents or construction contract law sections of your reference materials.

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.