EstatePass
Contract AdminContractshard40% of exam part

During contract closeout, the contractor discovers that $8,000 in retainage is being withheld for warranty items that were completed satisfactorily. The owner claims the items may fail during the warranty period. What is the contractor's best course of action?

Correct Answer

A) Request a warranty bond in lieu of cash retention

Requesting a warranty bond allows the contractor to receive the retained funds while still providing the owner security for warranty obligations. This is a common and reasonable solution during closeout.

Answer Options
A
Request a warranty bond in lieu of cash retention
B
Agree to extended retention for the specific warranty items only
C
Demand immediate release since the work was completed satisfactorily
D
Accept the retention since warranty coverage is required

Why This Is the Correct Answer

Requesting a warranty bond in lieu of cash retention is the best solution because it provides the owner with financial security for warranty obligations while allowing the contractor to receive their retained funds immediately. This approach balances both parties' interests - the owner gets protection against potential warranty claims, and the contractor gets their money without having to wait through the entire warranty period. Warranty bonds are a standard industry practice and are typically accepted by owners as adequate security.

Why the Other Options Are Wrong

Option B: Agree to extended retention for the specific warranty items only

Demanding immediate release ignores the owner's legitimate concern about warranty obligations and doesn't offer any alternative security, which could damage the business relationship and may not be legally enforceable.

Option D: Accept the retention since warranty coverage is required

Simply accepting the retention is not the best course of action because it unnecessarily ties up the contractor's funds when there are better alternatives available that protect both parties' interests.

Memory Technique

Think 'Bond = Best of Both' - warranty bonds serve both parties' interests better than cash retention

Reference Hint

Florida Building Code Chapter 1, Section 107 - Submittal Documents, and contract administration sections dealing with retainage and warranty provisions

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.