EstatePass
NASCLAProject Mgmthard22% of exam part

During project closeout, which document should be provided to the owner FIRST before conducting the final walkthrough?

Correct Answer

C) Operation and maintenance manuals

Operation and maintenance manuals should be provided before the final walkthrough so the owner can understand system operations during the walkthrough and ask questions about maintenance procedures.

Answer Options
A
Warranty information
B
Certificate of occupancy
C
Operation and maintenance manuals
D
Final invoice and lien waivers

Why This Is the Correct Answer

Operation and maintenance manuals should be provided before the final walkthrough so the owner can understand system operations during the walkthrough and ask questions about maintenance procedures.

Was this explanation helpful?

More NASCLA Questions