A foundation plan shows a footing detail with dimensions 3'-0" x 3'-0" x 1'-6" supporting a 12" x 12" column. What is the bearing pressure if the total load is 45,000 pounds?
Correct Answer
B) 5,000 psf
Bearing pressure = Total load ÷ Footing area. Area = 3' × 3' = 9 sq ft. Pressure = 45,000 lbs ÷ 9 sq ft = 5,000 psf.
Why This Is the Correct Answer
Bearing pressure = Total load ÷ Footing area. Area = 3' × 3' = 9 sq ft. Pressure = 45,000 lbs ÷ 9 sq ft = 5,000 psf.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
During project closeout, which document should be provided to the owner FIRST before conducting the final walkthrough?
Next Question
A subcontractor's work is 30 days behind schedule due to their own delays. The general contractor faces liquidated damages of $2,500 per day from the owner. What is the subcontractor's likely liability under a typical flow-down clause?
