During lockout/tagout procedures, an employee discovers that a machine has multiple energy sources (electrical, pneumatic, and hydraulic). What is the correct procedure?
Correct Answer
D) Lock out all energy sources and verify zero energy state
OSHA 29 CFR 1926.417 requires that ALL energy sources be locked out and the zero energy state be verified before beginning work on equipment.
Why This Is the Correct Answer
OSHA 29 CFR 1926.417 requires that ALL energy sources be locked out and the zero energy state be verified before beginning work on equipment.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15Β°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
During roof installation, the waterproofing membrane shows wrinkles and bubbles after application. What is the most likely cause and solution?
Next Question
A project has the following activities: A(5 days), B(8 days), C(6 days), D(4 days). Activity B starts after A, C starts after A, and D starts after both B and C are complete. What is the total project duration?
