A project has the following activities: A(5 days), B(8 days), C(6 days), D(4 days). Activity B starts after A, C starts after A, and D starts after both B and C are complete. What is the total project duration?
Correct Answer
B) 17 days
Path 1: A(5) + B(8) + D(4) = 17 days. Path 2: A(5) + C(6) + D(4) = 15 days. The longest path determines project duration: 17 days.
Why This Is the Correct Answer
The critical path method requires identifying all possible paths and selecting the longest duration. Path 1: A(5) → B(8) → D(4) = 17 days. Path 2: A(5) → C(6) → D(4) = 15 days. Since D cannot start until both B and C are complete, the project duration is determined by the longest path, which is 17 days through activities A-B-D.
Why the Other Options Are Wrong
Option A: 19 days
19 days incorrectly assumes activities run sequentially without considering parallel execution. This would be A+B+C+D, but C runs parallel to B after A completes, not sequentially after B.
Option C: 23 days
23 days represents the sum of all activity durations (5+8+6+4), ignoring that some activities can run in parallel. This approach fails to recognize the network logic and parallel paths.
Option D: 21 days
21 days might result from incorrectly calculating parallel activities or misunderstanding the precedence relationships. This doesn't match either valid path calculation through the project network.
Memory Technique
Remember 'Longest Path Wins' - in project scheduling, the critical path (longest duration path) determines total project time, not the sum of all activities.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
During lockout/tagout procedures, an employee discovers that a machine has multiple energy sources (electrical, pneumatic, and hydraulic). What is the correct procedure?
Next Question
On architectural drawings, what does the symbol consisting of a circle with a diagonal line and number typically represent?
