EstatePass
NASCLAProject Mgmtmedium22% of exam part

A project has the following activities: A(5 days), B(8 days), C(6 days), D(4 days). Activity B starts after A, C starts after A, and D starts after both B and C are complete. What is the total project duration?

Correct Answer

B) 17 days

Path 1: A(5) + B(8) + D(4) = 17 days. Path 2: A(5) + C(6) + D(4) = 15 days. The longest path determines project duration: 17 days.

Answer Options
A
19 days
B
17 days
C
23 days
D
21 days

Why This Is the Correct Answer

The critical path method requires identifying all possible paths and selecting the longest duration. Path 1: A(5) → B(8) → D(4) = 17 days. Path 2: A(5) → C(6) → D(4) = 15 days. Since D cannot start until both B and C are complete, the project duration is determined by the longest path, which is 17 days through activities A-B-D.

Why the Other Options Are Wrong

Option A: 19 days

19 days incorrectly assumes activities run sequentially without considering parallel execution. This would be A+B+C+D, but C runs parallel to B after A completes, not sequentially after B.

Option C: 23 days

23 days represents the sum of all activity durations (5+8+6+4), ignoring that some activities can run in parallel. This approach fails to recognize the network logic and parallel paths.

Option D: 21 days

21 days might result from incorrectly calculating parallel activities or misunderstanding the precedence relationships. This doesn't match either valid path calculation through the project network.

Memory Technique

Remember 'Longest Path Wins' - in project scheduling, the critical path (longest duration path) determines total project time, not the sum of all activities.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.