During construction, the owner requests additional work that will increase the contract time by 15 days and cost by $75,000. What document should be executed before proceeding with this work?
Correct Answer
C) Change order
A change order is the proper document to authorize changes to the contract scope, time, or cost. It should be executed before proceeding with additional work to ensure proper authorization and documentation.
Why This Is the Correct Answer
A change order is the correct document to formally authorize modifications to the contract's scope, cost, and/or schedule. It is a written agreement signed by the owner, contractor, and (under AIA documents) the architect that amends the original contract. The change order should be executed before proceeding to ensure all parties agree to the new terms and the contractor has authorization to perform the additional work.
Why the Other Options Are Wrong
Option A: Payment application
A payment application is submitted by the contractor to request payment for work already performed under the existing contract. It documents completed work for billing purposes β it does not authorize new or additional work beyond the contract scope.
Option B: Notice to proceed
A notice to proceed is issued at the start of a project to authorize the contractor to begin work under the original contract. It is not used to authorize changes or additions to work during construction.
Option D: Certificate of substantial completion
A certificate of substantial completion is issued near the end of the project when the work is sufficiently complete for the owner to occupy and use the project. It marks a milestone β it does not authorize additional work during ongoing construction.
Memory Technique
Any change to Scope + Time + Cost = Change Order. Remember the three S's: if the owner asks for Something extra that changes Schedule or Spending, you need a Change Order before you start.
More NASCLA Questions
How long should daily reports and project correspondence typically be retained after project completion?
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
On an electrical plan, a rectangle with three parallel lines inside typically represents:
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Which mortar type is most appropriate for exterior walls below grade that will be subject to high lateral earth pressure?
Next Question
During bid preparation, a contractor discovers an apparent error in the project specifications where two different concrete strengths are specified for the same foundation element. What is the most appropriate action?