EstatePass
NASCLAEstimatingmedium18% of exam part

During bid preparation, a contractor discovers an apparent error in the project specifications where two different concrete strengths are specified for the same foundation element. What is the most appropriate action?

Correct Answer

C) Submit a request for information (RFI) to the owner/architect

When discrepancies are found in contract documents, the proper procedure is to submit an RFI to get clarification from the design team before bidding. This ensures compliance and protects all parties.

Answer Options
A
Bid using the higher strength concrete to be safe
B
Bid using the lower strength concrete to be competitive
C
Submit a request for information (RFI) to the owner/architect
D
Include both options as alternates in the bid

Why This Is the Correct Answer

When discrepancies are found in contract documents, the proper procedure is to submit an RFI to get clarification from the design team before bidding. This ensures compliance and protects all parties.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.