During bid preparation, a contractor discovers an apparent error in the project specifications where two different concrete strengths are specified for the same foundation element. What is the most appropriate action?
Correct Answer
C) Submit a request for information (RFI) to the owner/architect
When discrepancies are found in contract documents, the proper procedure is to submit an RFI to get clarification from the design team before bidding. This ensures compliance and protects all parties.
Why This Is the Correct Answer
When discrepancies are found in contract documents, the proper procedure is to submit an RFI to get clarification from the design team before bidding. This ensures compliance and protects all parties.
More NASCLA Questions
How long should daily reports and project correspondence typically be retained after project completion?
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
On an electrical plan, a rectangle with three parallel lines inside typically represents:
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
During construction, the owner requests additional work that will increase the contract time by 15 days and cost by $75,000. What document should be executed before proceeding with this work?
Next Question
During a bid opening, a contractor discovers their bid is significantly lower than all others. What is the most appropriate first action?