EstatePass
Contract AdminProcedureseasy13% of exam part

During construction, the architect requests that the HVAC ductwork be relocated 3 feet to the east from the original design. What documentation should be prepared?

Correct Answer

D) As-built drawings showing the new location

As-built drawings must be prepared to document the actual installed location of the ductwork, which differs from the original design. This ensures accurate records for future maintenance and modifications.

Answer Options
A
A revised construction schedule
B
An updated material list
C
A change order only
D
As-built drawings showing the new location

Why This Is the Correct Answer

As-built drawings are the primary documentation required when actual construction deviates from the original design plans. These drawings record the exact location and configuration of installed systems as they were actually built, not as originally designed. For HVAC ductwork relocation, as-built drawings ensure that future maintenance, repairs, or modifications can be performed accurately since technicians will know the true location of the ductwork. This documentation is essential for building operations and is typically required by building codes and professional standards.

Why the Other Options Are Wrong

Option A: A revised construction schedule

A revised construction schedule addresses timing and sequencing of work but doesn't document the physical location changes of the installed ductwork. Schedule updates don't provide the spatial documentation needed for future reference.

Option B: An updated material list

An updated material list might be needed if different materials are required, but it doesn't document the actual installed location of the ductwork. Material lists address quantities and specifications, not spatial positioning.

Option C: A change order only

While a change order may be needed for cost and contract modifications, it doesn't provide the technical documentation of where the ductwork was actually installed. Change orders address contractual and financial aspects but don't serve as construction records.

Memory Technique

Think 'AS-BUILT = AS it was ACTUALLY BUILT' - whenever actual construction differs from plans, as-built drawings document reality.

Reference Hint

Florida Building Code, Chapter 1, Section 107 (Submittal Documents) and AIA Contract Documents regarding as-built drawing requirements

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.