EstatePass
Contract AdminContractseasy40% of exam part

An owner requests a change that will add $35,000 to the contract price and 12 days to the schedule. The contractor's markup on changes is 15% for overhead and profit. What should be the total change order amount?

Correct Answer

C) $40,250

The change order amount should include the direct cost plus the contractor's markup. $35,000 × 1.15 (15% markup) = $40,250. The time extension is typically handled separately from the cost adjustment.

Answer Options
A
$47,250
B
$35,000
C
$40,250
D
$52,500

Why This Is the Correct Answer

The correct change order amount must include both the direct cost of the change and the contractor's markup for overhead and profit. The $35,000 represents the direct cost of the change work, but contractors are entitled to add their markup to cover overhead expenses and profit margin. Multiplying $35,000 by 1.15 (which represents 100% of the cost plus 15% markup) gives $40,250. The 12-day schedule extension is handled as a separate contract modification and doesn't affect the monetary calculation.

Why the Other Options Are Wrong

Option A: $47,250

Option C of $47,250 would represent a 35% markup ($35,000 × 1.35), which is significantly higher than the stated 15% markup and would overcharge the owner.

Option B: $35,000

Option A only includes the direct cost of $35,000 without any markup for overhead and profit, which would result in the contractor losing money on the change order since they need to cover their business expenses and earn a reasonable profit.

Memory Technique

Remember 'CAMP' - Cost × (1 + Markup Percentage) = Total. The 'A' reminds you to ADD the markup to 1.00, not just multiply by the markup percentage alone.

Reference Hint

Look up contract administration and change order procedures in Chapter 7 of the Florida Building Contractor Reference Manual, specifically sections on markup calculations and change order pricing.

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.