During a foundation inspection in Hawaii, you find pahoehoe lava rock at the excavation bottom. The architect specifies a 2-foot deep foundation. What is the most appropriate action?
Correct Answer
B) Consult the engineer about bearing on rock surface
Pahoehoe lava rock provides excellent bearing capacity, but the foundation design should be reviewed by the engineer since the bearing conditions differ from the original soil assumptions.
Why This Is the Correct Answer
When the actual subsurface conditions differ from those assumed during design, the engineer of record must be consulted. Pahoehoe lava rock has high bearing capacity — often exceeding soil — but the foundation design was based on different assumed conditions. The engineer must confirm whether the existing design is appropriate for bearing on rock or requires modification (e.g., depth, reinforcement, anchor bolts into rock).
Why the Other Options Are Wrong
Option A: Excavate deeper into the rock as specified
Excavating deeper into solid rock per the original specification is unnecessary and potentially destructive. The specification assumed soil conditions; solid rock at the bottom may eliminate the need for the specified depth. Proceeding without engineering review ignores the changed conditions.
Option C: Add gravel base before pouring concrete
Adding a gravel base before pouring concrete is inappropriate when bearing on solid rock. Gravel bases are used to improve drainage and provide a working surface over poor soils — they are not needed on solid rock and would actually reduce the load path efficiency.
Option D: Pour concrete directly on the rock surface
Pouring concrete directly on rock without engineering review bypasses the engineer's authority over design changes. Even though rock is often better than soil, the contractor cannot unilaterally make this substitution — the engineer must approve the changed bearing conditions.
Memory Technique
Unexpected condition = call the engineer. Always. Even good surprises (solid rock instead of soil) require engineering sign-off. Remember: 'Surprise in the hole? Call before you pour.'
More Hawaii Questions
A concrete mix design for coastal construction specifies a water-cement ratio of 0.40. If 650 lbs of cement is used per cubic yard, how many gallons of water should be added?
A contractor is installing hurricane straps rated at 1,500 pounds each. If the calculated uplift force on a rafter is 3,200 pounds, how many straps are required with a 2.0 safety factor?
Hawaii Building Code requires special inspection for concrete placement in seismic design categories. What is the minimum frequency for concrete strength testing?
What is the maximum allowable deflection for roof rafters under design wind loads in Hawaii's hurricane zones?
Which roofing attachment method is specifically required in Hawaii's hurricane zones for asphalt shingles on residential construction?
A building in Maui requires hurricane straps rated for 175 mph winds. If each strap must resist 1,200 lbs of uplift force and you have 48 roof-to-wall connections, what is the total uplift resistance provided?
During construction of a beachfront property, you notice white crystalline deposits forming on the concrete surface. This indicates:
You discover expansive clay soil conditions during excavation for a residential foundation in Kona. The plasticity index is 28. What foundation system is most appropriate?
According to Hawaii building requirements, hurricane straps connecting roof trusses to wall plates must be rated for what minimum uplift force in high wind zones?
A concrete slab foundation in Hawaii requires a vapor barrier. Due to high humidity and frequent rainfall, what type of vapor barrier is most appropriate?