EstatePass
Contract AdminProceduresmedium13% of exam part

During a construction coordination meeting, the electrical subcontractor reports they cannot install conduit until the structural steel is in place, but the steel contractor is delayed by 3 days. What should the general contractor do first?

Correct Answer

A) Analyze the schedule impact and determine if the delay affects the critical path

The first step is to analyze the schedule impact to determine if this delay affects the critical path or if there is available float. This analysis will inform the appropriate response.

Answer Options
A
Analyze the schedule impact and determine if the delay affects the critical path
B
Terminate the steel contractor for breach of contract
C
Immediately notify the owner of a project delay
D
Hire additional workers to make up the lost time

Why This Is the Correct Answer

Analyzing the schedule impact and determining if the delay affects the critical path is the proper first step in project management. This analysis provides the factual basis needed to make informed decisions about next steps. Without understanding whether the delay has float or impacts the critical path, any other action would be premature and potentially unnecessary or harmful to project relationships.

Why the Other Options Are Wrong

Option B: Terminate the steel contractor for breach of contract

Hiring additional workers is a costly solution that may not address the actual problem and assumes the delay impacts the critical path. This decision should only be made after proper schedule analysis confirms it's necessary.

Option C: Immediately notify the owner of a project delay

Terminating the steel contractor would be an extreme overreaction without first understanding the contract terms, reasons for delay, and actual impact on the project. This could lead to legal issues and further project delays.

Memory Technique

Think 'STOP and ANALYZE' - before any major project decision, stop and analyze the schedule impact first

Reference Hint

Project Management chapter - Critical Path Method (CPM) and schedule analysis sections

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.