Under AIA A201, what is the time limit for the architect to respond to a contractor's claim for additional time or money?

Correct Answer

A) 21 days

AIA A201 requires the architect to respond to contractor claims within 21 days of receipt. This timeframe ensures timely resolution of issues and keeps the project moving forward.

Answer Options
A
21 days
B
7 days
C
10 days
D
30 days

Why This Is the Correct Answer

Under AIA A201 General Conditions, Section 15.1.3 specifically requires the architect to take action on contractor claims within 21 days after receipt of the claim. This timeframe applies to claims for additional time, money, or both. The 21-day period ensures adequate time for the architect to review documentation, consult with the owner, and make an informed decision while maintaining project momentum and avoiding unnecessary delays in the claims resolution process.

Why the Other Options Are Wrong

Option B: 7 days

Thirty days exceeds the timeframe required under AIA A201. While this might provide ample time for review, the contract specifically limits the architect's response time to 21 days to prevent excessive delays in claims resolution that could impact project schedules and contractor cash flow.

Option D: 30 days

Seven days is too short a timeframe under AIA A201. This brief period would not provide the architect sufficient time to properly review claim documentation, investigate the merits, consult with the owner, and render a thoughtful decision on potentially complex issues involving additional time or compensation.

Memory Technique

Remember '21 days for AIA' - think 'three weeks to weigh' the architect's decision on contractor claims.

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.