A subcontractor fails to complete work on schedule, causing project delays. Under a typical subcontract agreement, what is the general contractor's primary remedy?

Correct Answer

B) Charge liquidated damages or actual delay costs

The primary remedy for subcontractor delays is typically to charge liquidated damages (if specified in the contract) or actual delay costs. This provides compensation for the damages caused by the delay while maintaining the contractual relationship.

Answer Options
A
Complete the work with own forces at subcontractor's expense
B
Charge liquidated damages or actual delay costs
C
Immediately terminate the subcontractor
D
Withhold all payments until work is completed

Why This Is the Correct Answer

Charging liquidated damages or actual delay costs is the primary remedy because it provides monetary compensation for the harm caused by delays while preserving the contractual relationship. This approach follows the fundamental contract law principle of making the injured party whole through damages. It's typically the first remedy pursued before considering more drastic measures like termination, as it allows the project to continue while addressing the financial impact of delays.

Why the Other Options Are Wrong

Option A: Complete the work with own forces at subcontractor's expense

Completing work with own forces at subcontractor's expense (called 'completion by others') is typically a secondary remedy used after other measures fail. It requires proper notice and procedures, and is more complex and risky than seeking monetary damages.

Option C: Immediately terminate the subcontractor

Withholding all payments can constitute a breach of contract by the general contractor and may violate prompt payment laws. Payments should only be withheld in proportion to incomplete or defective work, not as a blanket remedy for delays.

Memory Technique

Think 'DOLLARS before DRASTIC' - seek monetary damages (dollars) before taking drastic actions like termination or taking over the work

Reference Hint

Florida Building Code - Chapter 1, Section 107 (Construction Documents and Inspections) and contract law sections dealing with breach remedies and damages

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.