EstatePass
VirginiaVA Supplementhard100% of exam part

Calculate the mechanics lien priority: First lien filed June 1st for $25,000, second lien filed May 15th for $18,000, both for work completed April 30th. Which has priority?

Correct Answer

C) Equal priority based on completion date

In Virginia, mechanics liens for work completed on the same project have equal priority regardless of filing order or amount, based on the work completion date.

Answer Options
A
Second lien due to earlier filing
B
First lien due to higher amount
C
Equal priority based on completion date
D
Priority determined by contract date

Why This Is the Correct Answer

Under Virginia mechanics lien law, all liens on a single project arising from work performed on or before the same commencement date share equal priority — they are not prioritized by filing date or lien amount. Because both liens relate to work completed on April 30th for the same project, they have equal priority. In a foreclosure or distribution scenario, proceeds would be shared pro-rata among equal-priority lienholders.

Why the Other Options Are Wrong

Option A: Second lien due to earlier filing

The second lien was filed earlier (May 15th vs. June 1st), but in Virginia, filing date does not determine priority for mechanics liens on the same project. Priority is based on the commencement of the work/project, not the order of lien filing.

Option B: First lien due to higher amount

Lien amount does not determine priority. The $25,000 lien has no advantage over the $18,000 lien simply because it is larger. Virginia law treats mechanics liens with the same project commencement date as equal in priority regardless of dollar amount.

Option D: Priority determined by contract date

Contract date is not the determining factor for lien priority under Virginia law. The relevant date is the commencement of the project (when the first work or materials were provided), not when contracts were signed.

Memory Technique

Think of Virginia mechanics liens as 'no race to the courthouse.' All subcontractors and suppliers on the same project share the pie equally, regardless of who filed first or for how much. Equal work completion date = equal priority = equal share.

Was this explanation helpful?

More Virginia Questions

Under Virginia law (Title 54.1), what is the minimum net worth requirement for a Class A contractor license?

A Virginia contractor fails to pay a subcontractor $18,500 for completed work. Under Virginia mechanics lien law, within how many days must the subcontractor file a memorandum of lien to preserve their lien rights?

A Virginia contractor employs 8 workers with a total annual payroll of $420,000. Using the standard construction rate of $8.50 per $100 of payroll, what is the annual workers' compensation premium?

A Virginia contractor fails to pay subcontractors on a $180,000 project. Under Virginia mechanics lien law, what is the maximum time period a subcontractor has to file a mechanics lien after last furnishing labor or materials?

Under Virginia contractor law, what happens to a contractor's license if they fail to maintain required insurance coverage?

A contractor fails to pay a subcontractor and the subcontractor files a mechanics lien. Under Virginia law, within how many days must the general contractor post a bond to release the lien from the property?

A Class B contractor in Virginia completed $850,000 worth of work in the current license period and has contracts totaling $1,200,000 for the next period. What action must the contractor take?

A homeowner hired an unlicensed contractor for a $45,000 kitchen renovation. Under Virginia law, what remedy is available to the homeowner?

Calculate the required bond amount for a Virginia Class A contractor with average annual gross receipts of $2,800,000 over the past three years.

A Class C contractor in Virginia wants to install a residential HVAC system valued at $12,000. The contractor's specialty classification is electrical work. What must the contractor do to legally perform this work?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.