Calculate the mechanics lien priority: First lien filed June 1st for $25,000, second lien filed May 15th for $18,000, both for work completed April 30th. Which has priority?

Correct Answer

C) Equal priority based on completion date

In Virginia, mechanics liens for work completed on the same project have equal priority regardless of filing order or amount, based on the work completion date.

Answer Options
A
Second lien due to earlier filing
B
First lien due to higher amount
C
Equal priority based on completion date
D
Priority determined by contract date

Why This Is the Correct Answer

In Virginia, mechanics liens for work completed on the same project have equal priority regardless of filing order or amount, based on the work completion date.

Was this explanation helpful?

More va-supplement Questions

Under Virginia law (Title 54.1), what is the minimum net worth requirement for a Class A contractor license?

A Virginia contractor fails to pay a subcontractor $18,500 for completed work. Under Virginia mechanics lien law, within how many days must the subcontractor file a memorandum of lien to preserve their lien rights?

A Virginia contractor employs 8 workers with a total annual payroll of $420,000. Using the standard construction rate of $8.50 per $100 of payroll, what is the annual workers' compensation premium?

A Virginia contractor fails to pay subcontractors on a $180,000 project. Under Virginia mechanics lien law, what is the maximum time period a subcontractor has to file a mechanics lien after last furnishing labor or materials?

Under Virginia contractor law, what happens to a contractor's license if they fail to maintain required insurance coverage?

A contractor fails to pay a subcontractor and the subcontractor files a mechanics lien. Under Virginia law, within how many days must the general contractor post a bond to release the lien from the property?

A Class B contractor in Virginia completed $850,000 worth of work in the current license period and has contracts totaling $1,200,000 for the next period. What action must the contractor take?

A homeowner hired an unlicensed contractor for a $45,000 kitchen renovation. Under Virginia law, what remedy is available to the homeowner?

Calculate the required bond amount for a Virginia Class A contractor with average annual gross receipts of $2,800,000 over the past three years.

A Class C contractor in Virginia wants to install a residential HVAC system valued at $12,000. The contractor's specialty classification is electrical work. What must the contractor do to legally perform this work?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.