According to Virginia mechanics lien law, within how many days must a subcontractor file a mechanics lien after last furnishing labor or materials?

Correct Answer

C) 90 days

Virginia Code § 43-4 requires subcontractors to file mechanics liens within 90 days after last furnishing labor, materials, or services to the project.

Answer Options
A
120 days
B
30 days
C
90 days
D
60 days

Why This Is the Correct Answer

Virginia Code § 43-4 sets the mechanics lien filing deadline for subcontractors at 90 days after the last furnishing of labor, materials, or services to the project. This is a strict statutory deadline — missing it forfeits lien rights.

Why the Other Options Are Wrong

Option A: 120 days

120 days is incorrect for Virginia subcontractors. The 120-day rule applies to North Carolina mechanics liens. Confusing these two neighboring states' rules is a very common exam mistake.

Option B: 30 days

30 days is incorrect. No Virginia lien statute imposes a 30-day filing deadline. This period is too short and is not found in Virginia lien law.

Option D: 60 days

60 days is incorrect. While 60 days appears in some lien-related preliminary notice contexts in other states, Virginia's lien filing deadline for subcontractors is 90 days — not 60.

Memory Technique

Virginia = 90 days. NC = 120 days. Memory shortcut: 'Virginia is the older state (comes first alphabetically nearby), so it gets the shorter window — 90 days.' Or: VA = 90, NC = 120 (V comes before N, 90 comes before 120).

Was this explanation helpful?

More Virginia Questions

Under Virginia law (Title 54.1), what is the minimum net worth requirement for a Class A contractor license?

A Virginia contractor fails to pay a subcontractor $18,500 for completed work. Under Virginia mechanics lien law, within how many days must the subcontractor file a memorandum of lien to preserve their lien rights?

A Virginia contractor employs 8 workers with a total annual payroll of $420,000. Using the standard construction rate of $8.50 per $100 of payroll, what is the annual workers' compensation premium?

A Virginia contractor fails to pay subcontractors on a $180,000 project. Under Virginia mechanics lien law, what is the maximum time period a subcontractor has to file a mechanics lien after last furnishing labor or materials?

Under Virginia contractor law, what happens to a contractor's license if they fail to maintain required insurance coverage?

A contractor fails to pay a subcontractor and the subcontractor files a mechanics lien. Under Virginia law, within how many days must the general contractor post a bond to release the lien from the property?

A Class B contractor in Virginia completed $850,000 worth of work in the current license period and has contracts totaling $1,200,000 for the next period. What action must the contractor take?

A homeowner hired an unlicensed contractor for a $45,000 kitchen renovation. Under Virginia law, what remedy is available to the homeowner?

Calculate the required bond amount for a Virginia Class A contractor with average annual gross receipts of $2,800,000 over the past three years.

A Class C contractor in Virginia wants to install a residential HVAC system valued at $12,000. The contractor's specialty classification is electrical work. What must the contractor do to legally perform this work?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.