According to Virginia environmental regulations, what is the minimum project size that requires a stormwater management plan for land-disturbing activities?
Correct Answer
D) 2,500 square feet
Virginia's Stormwater Management Law requires permits for land-disturbing activities of 2,500 square feet or greater.
Why This Is the Correct Answer
Virginia's Stormwater Management Act and the Virginia Stormwater Management Program (VSMP) regulations require that land-disturbing activities affecting 2,500 square feet or more must obtain a permit and implement a stormwater management plan. This threshold is notably lower than the federal 1-acre threshold under the Clean Water Act, reflecting Virginia's stricter local requirements.
Why the Other Options Are Wrong
Option A: 5,000 square feet
5,000 square feet is double the actual Virginia threshold. While some jurisdictions use 5,000 sq ft as a trigger, Virginia's VSMP sets the bar at 2,500 sq ft. Using the higher figure would leave many regulated projects without required stormwater controls.
Option B: 10,000 square feet
10,000 square feet significantly overstates the Virginia threshold and appears to be a distractor based on municipal-level ordinances in some localities. Virginia state law is more stringent at 2,500 sq ft.
Option C: 1 acre
1 acre (43,560 sq ft) is the federal EPA threshold for stormwater permits under the NPDES Construction General Permit. Virginia has adopted a stricter standard of 2,500 sq ft, so relying on the federal threshold underestimates Virginia's requirements.
Memory Technique
Virginia stormwater = 2,500 sq ft. Think: '2,500 — a small lot triggers Virginia's controls.' A typical one-car garage footprint is about 400 sq ft; 2,500 sq ft is roughly a modest house footprint. Virginia is strict — even disturbing a small house footprint of dirt requires a stormwater plan.
More Virginia Questions
Under Virginia law (Title 54.1), what is the minimum net worth requirement for a Class A contractor license?
A Virginia contractor fails to pay a subcontractor $18,500 for completed work. Under Virginia mechanics lien law, within how many days must the subcontractor file a memorandum of lien to preserve their lien rights?
A Virginia contractor employs 8 workers with a total annual payroll of $420,000. Using the standard construction rate of $8.50 per $100 of payroll, what is the annual workers' compensation premium?
A Virginia contractor fails to pay subcontractors on a $180,000 project. Under Virginia mechanics lien law, what is the maximum time period a subcontractor has to file a mechanics lien after last furnishing labor or materials?
Under Virginia contractor law, what happens to a contractor's license if they fail to maintain required insurance coverage?
A contractor fails to pay a subcontractor and the subcontractor files a mechanics lien. Under Virginia law, within how many days must the general contractor post a bond to release the lien from the property?
A Class B contractor in Virginia completed $850,000 worth of work in the current license period and has contracts totaling $1,200,000 for the next period. What action must the contractor take?
A homeowner hired an unlicensed contractor for a $45,000 kitchen renovation. Under Virginia law, what remedy is available to the homeowner?
Calculate the required bond amount for a Virginia Class A contractor with average annual gross receipts of $2,800,000 over the past three years.
A Class C contractor in Virginia wants to install a residential HVAC system valued at $12,000. The contractor's specialty classification is electrical work. What must the contractor do to legally perform this work?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A homeowner hires a contractor for $8,500 worth of work. The contractor completes the job but the homeowner refuses to pay, claiming defective work. Under Virginia mechanics lien law, what is the contractor's maximum lien amount if the work was actually worth $7,200?
Next Question
According to Virginia Code Title 54.1, how often must a contractor renew their license?